Pending a final investment decision, expected in 2025, offshore construction for Nordlicht I and II is anticipated to begin in 2026, with full operational status scheduled for 2028.
Vattenfall develops the sites and has now awarded several contracts for the construction of both wind farms. Jan De Nul had earlier won the contract to install inter-array cables that transmit electricity between offshore wind turbines.
Jan De Nul will install 196 kilometres of cables and ensure their connection to 112 wind turbines.