Türkiye’s first floating natural gas production platform, named “Osman Gazi,” was expected to pass through the Bosporus on Thursday and head to Filyos Port on the Black Sea coast, where it is expected to start operating next year.

The platform’s passage comes on the 572nd anniversary of the conquest of Istanbul.

The floating production unit (FPU), which docked in Çanakkale last year after being acquired a year before, was given the name “Osman Gazi” earlier this week and is seen as a notable addition to the country’s energy fleet as it looks the curb the dependence on foreign energy sources and boost domestic gas and oil production.

The platform is poised to complement the energy landscape by doubling natural gas production in the Black Sea region, the Energy and Natural Resources Minister Alparslan Bayraktar said on Tuesday.

The platform was expected to depart from Ahırkapı at 11:00 a.m. local time and was projected to be in front of the iconic Dolmabahçe Palace in the center of Istanbul in the afternoon.

Turkish media reported that ship traffic in the Bosporus has been suspended in both directions due to the passage of the massive vessel.

The “Osman Gazi” was set to be sent off to the Black Sea from Dolmabahçe Palace with a farewell ceremony attended by President Recep Tayyip Erdoğan and Bayraktar.

The Bosporus passage will take approximately 11 hours, and Osman Gazi is planned to dock at Filyos Port on June 1, an Anadolu Agency (AA) report said.

“If you want to witness history, turn your face to the Bosporus! Türkiye’s first Floating Production Platform is passing through the Bosporus with the largest towing operation in the history of the republic,” Bayraktar said in a post on X.

“This giant facility is accompanied by five tugboats, led by Nene Hatun, which is among the top three in the world with its 205 tons of traction power. Just like in 1453, this unique transition will be a victory of determination, perseverance and Turkish engineering that will leave its mark on history,” he added.

Osman Gazi is expected to start its duty in the Black Sea in 2026, doubling the current natural gas output there, the minister said earlier this week.

“Thus, with a daily production of 20 million cubic meters (mcm), we will meet the natural gas needs of 8 million households from the Sakarya Gas Field,” he noted.

Sakarya Gas Field is Türkiye’s flagship natural gas field, producing currently 9.5 mcm of gas daily.

Osman Gazi platform’s maximum natural gas processing capacity is 10.5 mcm and its maximum gas transfer capacity is 10 mcm.

Measuring 298.5 meters (979.3 feet) in length, 56 meters in width and 29.5 meters in depth, it has a personnel capacity of 140 people.

The main gas transmission line from the platform to the land will be 161 kilometers long. The natural gas processed on the platform will be delivered to the land via this line and given to the national grid in a ready-to-use form.

The Daily Sabah Newsletter

Keep up to date with what’s happening in Turkey,
it’s region and the world.

SIGN ME UP

You can unsubscribe at any time. By signing up you are agreeing to our Terms of Use and Privacy Policy.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.