The Golden Pass LNG export terminal under construction on the Texas coast nominated feed gas for the first time late Thursday.
Expand
The evening cycle for Friday’s gas day shows Golden Pass nominated 4,067 Dth, or roughly 4 MMcf, of feed gas, according to data collected by NGI. The nomination doesn’t necessarily mean gas is flowing to the facility, but it was requested for the first time as Golden Pass ramps up commissioning activities.
The 18 million tons/year project requested authorization from FERC earlier this month to introduce fuel gas to power boilers at the facility. It also requested permission to introduce hazardous fluids and fuel gas to the flare system. FERC has not yet authorized those requests.