The Texas Senate Committee on Water, Agriculture, and Rural Affairs heard testimony during an interim hearing on Tuesday regarding water usage for data centers.

Data centers have become a focal point for the November midterm election and for the 90th Legislative Session beginning in January.

“I think every [Texas Legislature] member’s district has had an impact from a data center conversation,” Chairman Charles Perry (R-Lubbock) said at the start of the hearing. 

Perry said that he has met and spoken with many of the data center developers, operators, and customers to prepare for the hearing, and believes that many of them are “good actors.” 

“But, as always, there are bad actors,” he continued, specifically calling out Beacon Data Centers, which is building the Westline Energy Infrastructure Campus in his district. According to Perry, Beacon has not answered phone calls or communicated on the local level. 

“They choose to operate in secrecy,” he stated. “And for that, and that alone, as of today, whatever I need to do to keep them from implementing wherever they’re going — I don’t believe they’re actually a data center.”

Perry said that data centers have become “way too much of a political football” and emphasized that it is “too big of an issue for Texas to get it wrong and it’s too big of an issue for us to ignore.” 

“The Legislature, county officials, [and] local officials have been beaten up politically and publicly because they should have done something about this,” he stated. “What this is is an industry that hit this state on a velocity that no one should have [seen] or could have [seen] coming.” 

During this election cycle, state lawmakers have come under fire for passing Senate Bill (SB) 2023, a bill that gives certain tax incentives for data centers, which Perry emphasized was passed in 2013, “preceding this governor.” 

“So, for the political rhetoric that we as a Legislature decided to incentivize AI data centers, the last two sessions, to come in here and do what they’re doing is just factually not accurate,” Perry stated. He added that data centers “saw an incentive that they qualified for and took advantage of it” — something he said he doesn’t “begrudge them for.” 

Perry, who said that he is neutral on the subject, believes data centers “provide a lot of good benefits,” but that the “ones that are irresponsible will never see the light of day.” 

Temple McKinnon, Director of the Water Supply Planning Division at the Texas Water Development Board (TWDB), spoke on the agency’s 2025 water use survey, which sent notices to 341 facilities identified as data centers — a number later refined to 324 after TWDB identified duplicate surveys and facilities that were not yet operational.

McKinnon reported that, as of August 26, TWDB had a 30 percent response rate among the facilities surveyed.

She also noted that the TWDB began coordinating with PUC in October 2025 on requirements under a budget rider in SB 1 during the 89th Legislative Session, specifically questions they thought “would collect useful water use data to better understand current and future, direct and indirect water use.” 

McKinnon clarified that the PUC survey was a “one-time ask of projected power use by data centers in the state upon which my agency will work to associate estimated future water use.”

Representatives from the Public Utility Commission of Texas (PUC) reported that it conducted a voluntary survey among certain industrial facilities “whose energy use and water use have an inverse relationship.” The PUC survey ran in two rounds, from April 2 to May 28 and again from July 1 to July 10.

“We had a fairly straightforward goal for that survey: we wanted to collect information about both energy use and water use from the facilities,” PUC Executive Director Connie Corona said. 

PUC received responses from 57 companies representing 168 facilities, 144 of which are data centers.

State Sen. Lois Kolkhorst (R-Brenham) said that the survey gives the committee a “pretty good sample of the good actors and the bad actors.” She emphasized that “they did not abide by the law” and said the survey request has been legally required for two years.

“As Texas continues to grow and new industries come online, we must have a clear understanding of our water use for long-term planning and to protect our resources,” state Sen. Cesar Blanco (D-El Paso) wrote in an X post on Tuesday.

Dr. Vaibhav Bahadur, associate professor of mechanical engineering at the University of Texas at Austin, highlighted that produced water, the naturally occurring wastewater that surfaces during the oil and natural gas extraction process, can be an option for cooling data centers. 

Despite the high salinity of produced water, Bahadur said that there is “a respectable fraction of produced water that can be treated more or less with today’s technologies.” Even with the potentially high cost of desalination, he stressed that produced water should be seriously considered as “a meaningful solution to the water issues of data centers.”

A panel of data center practitioners, including Lancium Technologies, Quality Technology Services (QTS), and Google, testified about the water and energy usage for their respective companies. 

“QTS — and several other good actors in the state — we pay for all infrastructure required to bring power to our sites. We pay for all of the energy that we consume,” QTS Senior Vice President of Facility Operations Ryan Kuithe told the committee. He said that the company has no intention of asking the residents or ratepayers to subsidize its growth, “nor is the expectation that they should subsidize the industry’s growth.”

Ben Townsend, head of infrastructure and sustainability at Google, said that all of the company’s planned data centers in Texas, including their locations in Haskell, Willbarger, and Armstrong Counties, “are conscientious of limited community water resources and are designed with advanced closed-loop air cooling systems that will help us eliminate freshwater consumption for cooling.”

Townsend also said that, beginning in 2023, Google became “the first major cloud provider to begin reporting site-level water use shared every year” in the company’s environmental report.

Perry told the panel of data center operators that if they are unwilling to communicate with the lawmakers, “the outcome’s not gonna be good in the Legislature.”

Kolkhorst said Texans haven’t had the chance to understand the breadth of data centers. 

“No one has ever defined it as explaining the applications and what is requiring this massive build-out … Is it for consumer AI? Medical research? Autonomous weapons? Financial markets? National defense? Digital identity? Or is it government surveillance?” she asked. “Or is it all of the above?”

State Sen. Roland Gutierrez (D-San Antonio) also touched on surveillance: “I wanna know who the hell’s looking inside my house, and my computer, and figuring out what the hell I’m gonna buy next. And what question I wanna ask next. People have a legitimate concern about that.”

City and county officials testified that they have not always been aware of data centers until a private land sale was already complete and the operator had begun working with utility companies.

Perry also spoke about how data centers start with the “landowners in the private sector, for the most part,” and that county commissioners and other local officials do not know “what’s being negotiated on the private level, nor should they.” 

Caldwell County Judge Hoppy Haden said that in every case in his county, data centers had “bought the land and had already had communication with the utility company” before appearing in his office.

Perry said that legislators need to be “really clear and really careful how we start meddling in the contract laws between private seller and private buyer.”

Perry asked Rick Thompson of the County Judges and Commissioners Association of Texas for a list of county judges with data centers in their jurisdictions that have not been communicating with local officials. 

“If they’re not willing to engage the community and help commissioners and city officials to get over the hump, then they’re not people that should be awarded state permitting,” Perry said. 

On whether the Legislature can statutorily require this communication, Perry said, “Let’s just say that there’s gonna be a hierarchy and enough people in the pipeline that those processes are still under our guise to work with.”

Johnson emphasized that while the organization wants reasonable guidelines to protect the communities, it’s not against data centers. 

“For counties in rural Texas, this is an opportunity for a livelihood,” he said. “Folks aren’t moving to rural Texas. They’re leaving rural Texas. The kids are leaving. There’s nothing for them in many places.”