General view of the Google headquarters in King's Cross as

LONDON, UNITED KINGDOM – 2025/04/17: General view of the Google headquarters in King’s Cross as the tech giant faces a 5 billion pound lawsuit in the UK for allegedly abusing its online search dominance. (Photo by Vuk Valcic/SOPA Images/LightRocket via Getty Images)

Google will put at least €13 billion, about $15.1 billion, into Finland across 2027 and 2028.

The money expands its Hamina data center and builds three new ones in Kajaani, Vaala and Muhos, the company’s largest single investment anywhere in Europe. Alongside it comes a 22-year contract for up to half the output of the Loviisa nuclear plant, Google’s first nuclear deal outside the United States.

Finland’s prime minister, Petteri Orpo, called the decision “a clear testament to our strengths” and talked about innovation, research and development. The more revealing number is the one his government now owns: 37,000 jobs attached to four sets of permits.

What Google bought in Finland is what Europe’s established data center hubs now ration most tightly: a grid and a government that says yes. The cash, the jobs, the wind farms and the nuclear contract are the price of that yes, and the price is public.

The economic side is built to be read out in a parliament.

Google says construction adds €3.6 billion a year to Finland’s GDP and supports more than 37,000 jobs. Once running, the four sites sustain about 7,000 jobs at wages 24% above the national median.

The energy side is where the real terms sit. Google contracted new onshore wind from two Finnish developers, is building a grid battery near Kajaani, and signed the nuclear agreement with Fortum. Every line runs the same direction: Google pays, Finland collects, and the permits become the easiest decision in Helsinki.

The Fortum deal is the anchor. Google takes up to half of Loviisa’s output from 2030 to 2049. Loviisa is two Soviet-designed reactors from the late 1970s that supply more than a tenth of Finland’s electricity.

Its license runs to 2050 only if Fortum completes an upgrade program priced at about €1 billion, and most of that spending had not yet been approved. Fortum has said that without the program the plant could not run past 2030.

Google’s signature is what makes those decisions easy, and Fortum’s shares rose 10% on the day.

Why Finland, And Why The Old Hubs Lost

Capital goes where it is most welcome and stays where it is best treated. In European data centers, that now means following grid access, and the old hubs are losing it.

Dublin froze new data center connections in 2022 and only reopened in December 2025 under strict conditions. Amsterdam’s connection queue runs about ten years. Frankfurt and London are not promising major grid upgrades until the early 2030s.

Denmark paused every new large connection from March to June this year, with a queue nearly nine times the country’s peak demand. The old hubs are rationing power by queue, and a queue is simply a no with a date on it.

The capacity followed the open doors. CBRE found that 63% of the data center capacity added in Europe last quarter went outside the five big hubs. Nordic AI signings nearly quintupled in a year, while Nebius is building an €8.5 billion site in eastern Finland.

Finland won this while raising taxes on data centers. From July, data centers pay the standard electricity tax instead of a reduced rate, a 45-fold increase. Google announced one of the largest investments in Finnish industrial history two months later.

The scarce input is grid access, and Finland is one of the few places in Europe still selling it. Any country can match a tax rate in an afternoon. A grid operator willing to connect four new campuses is rarer, and Fingrid’s chief executive said the chosen sites sit at strong points on the network.

The Big Tech Nuclear Pattern

Loviisa extends a pattern in which Big Tech companies become anchor tenants of aging nuclear plants. Microsoft agreed to restart Three Mile Island. Google signed a 25-year deal with NextEra to bring back the Duane Arnold plant in Iowa, which shut down in 2020.

Now Google has exported the model.

The structure is the same each time. The utility gets a contract long enough to justify spending it might otherwise delay. The plant gets a second life. The government keeps a large share of its power supply running and gets to announce jobs.

The tech company gets reliable, carbon-free power for two decades at a price it can plan around, which is the input everything else in its budget depends on.

Alphabet expects to spend up to $205 billion on capital projects this year. Spread over two years, the Finland package costs under 4% of one year’s budget. In return, Google gets four sites with grid connections and a power contract running to 2049.

The price of political consent has become a small, recurring line in Big Tech’s capital spending, and what it buys is demand that runs to 2049. Expect the template to be copied. Once one government accepts jobs, GDP and a rescued power plant in exchange for permits, the next has to explain why it turned the same offer down.

The risks are mostly about timing. Permits can drag, grid work can slip, and Fingrid has already restricted new connections in parts of southern Finland through 2027. The Loviisa upgrade still has to be carried out on an old plant, and a future government can change tax policy, as this one just did.

None of that changes the direction. The capacity becomes harder to walk away from once construction starts.