A railway line in Hradec Králové, in eastern Czech Republic, is to be fully modernised as part of a project estimated at EUR 284.5 million (CZK 6.9 billion). Work is scheduled to begin in March 2027 and be completed by the end of 2029.
The project covers 20 km of railway between Hradec Králové and Týniště nad Orlicí, and the Czech railway infrastructure manager, Správa železnic, has launched the tender for the works.
The main work will involve doubling the track, which will allow a greater number of trains to run. At the same time, the maximum speed will increase from 100 to 160 km/h, and journey times will be reduced by up to seven minutes.
The project also involves the installation of the ETCS system and the electrification of the line, which will enable the operation of electric trains and the more efficient integration of the route into the Czech Republic’s modernised rail network.
The modernisation involves the reconstruction of the track and points, as well as work on embankments, viaducts and bridges. The new platforms will be 550 mm above the top of the rail to facilitate passenger access.
The tender has been divided into three components: infrastructure, power supply, and signalling and communications systems. According to the Ministry of Transport, this structure aims to attract a larger number of bidders and create a competitive environment, which may help to reduce costs.
Work is scheduled to begin in March 2027 and be completed by the end of 2029.
An alternative route for the main rail corridor
The importance of the project extends beyond regional traffic, as the route between Hradec Králové station and Týniště nad Orlicí forms part of the alternative route for the main corridor passing through Pardubice and Česká Třebová, and is capable of handling both passenger and freight trains. The modernisation and doubling of the track will thus increase the capacity and resilience of the Czech rail network, including in situations where traffic needs to be diverted from the main route.
All stations and halts along the route will be modernised, and the platforms will be replaced with new ones, accessible to people with reduced mobility and equipped with information and wayfinding systems.
At Hradec Králové-Slezské Předměstí and Třebechovice pod Orebem stations, access to trains will be via underground pedestrian underpasses.
The project also includes works to improve road and rail safety. Nine level crossings will be rebuilt, and in Třebechovice pod Orebem the level crossing will be replaced by an overpass.