The West Virginia Public Service Commission’s Charleston headquarters is pictured in this 2022 photo.
Gazette-Mail file
“Do you believe that the MARL project carries material, useful benefits for West Virginia?
That question and answer provided by the West Virginia Public Service Commission staff in formal case testimony filed Tuesday sums up its dim view of a $1.16 billion interstate power line project also heavily opposed by consumer advocates and landowners that would be affected along the project route slated to cross parts of Pennsylvania, Maryland and Virginia, in addition to the Mountain State.
The project is NextEra Transmission MidAtlantic Inc.’s MidAtlantic Resiliency Link project, a planned 107.5-mile, 500-kilovolt transmission line known as MARL planned to consist of roughly 59 miles of transmission line and related facilities in Monongalia, Preston, Mineral and Hampshire counties.
The PSC staff’s newly submitted formal opposition to the project is notable given the staff is a wing of the PSC itself and that the testimony cited what staff indicated was project-damning field work that its technical analyst Daniel Egnatoff conducted consisting of visits to roughly 80 landowners at their properties all located within the MARL study area.
“Several concerns were raised by nearly every impacted landowner,” Egnatoff testified, reporting that property value and financial hardship, loss of land use, health and safety, and behavior of applicant representatives as the main worries he found.
Accompanying PSC staff’s opposition in recent days have been other formal filings of testimony registering opposition from dozens of landowners.
“I respectfully ask the Commission to reject a route that would place this project so extraordinarily close to our residence and permanently change the home and retirement we have worked so hard for,” Susan Marteney said in direct testimony submitted Aug. 31, referencing her and her husband Scott’s Springfield, Hampshire County home, reporting project plans show a structure pad limit of disturbance next to a proposed 500-kilovolt transmission tower roughly 105 feet from the back of their home.
In testimony filed Tuesday on behalf of West Virginians Against Transmission Injustice, a nonpartisan grassroots group formed in May 2025 because of concerns regarding MARL and another interstate power line project, Valley Link, independent, Charleston-based energy analyst Cathy Kunkel estimated MARL would cost West Virginia electricity customers more than $210 million during its construction and first 15 years of operation, and roughly $400 million during the lifetime of the project.
The flurry of filings come after the PSC denied a NextEra request to push back the decision due date in its case by 11 weeks until May 22, 2027, with other 11-week case deadline delays, a request which had followed a PSC staff recommendation for case delays.
PSC staff had said more time was needed for landowners newly projected to be affected by the project to have due process and participate in the hearing and for staff to investigate. But in a Sept. 4 ruling that touted “the importance of a strict schedule in this transmission certificate proceeding,” the PSC held that unresolved regulatory or planning issues didn’t require suspending or delaying the case.
The tidal wave of formal testimony against MARL comes days after Kaitlin McCormick, senior director of development at NextEra affiliate NextEra Energy Transmission LLC, contended at last week’s West Virginia Chamber of Commerce Annual Business Meeting & Summit at the Greenbrier that MARL was key to strengthening infrastructure supporting economic growth across the regional power grid operated by PJM Interconnection LLC, which recommended the project following projected electricity demand growth from data centers in Virginia.
“In this new era of unprecedented electricity demand, staying connected means staying competitive,” McCormick said at her Sept. 3 summit appearance. “That’s what the Mid-Atlantic Resiliency Link is all about.”
Christian Beam, president of FirstEnergy’s West Virginia and Maryland operations, testified to the PSC in a separate case in July that it would adversely impact the ability of a proposed $2.47 billion gas-fired power plant the company plans to build and operate at the end of 2031 in Monongalia County to transport power if the MARL line “would go away.”
The office of Gov. Patrick Morrisey, a proponent of the proposed gas plant, did not respond to a request for comment on whether he supports the MARL project.
PSC staff: MARL doesn’t meet ‘necessary level of diligence’
On behalf of PSC staff, Egnatoff testified that West Virginia’s energy infrastructure is not “at severe risk” if the MARL line isn’t built, finding that growth in data center use is served by entities unlikely to abandon efforts at safe and dependable operation, connecting and energizing high-use customers knowing that doing so would overload the transmission grid and inflict vast damage.
“The most likely outcome of the MARL Project not being built is the energizing of fewer data centers in Virginia,” Egnatoff testified.
Egnatoff testified that NextEra “has not proven that it engaged in the necessary level of diligence regarding a project of this scale.”
The technical analyst pointed to NextEra erroneously stating that American Electric Power subsidiary customers would see no rate impact from the project, failing to notify an impacted landowner and then not notifying the PSC that that had occurred, requiring it to make “material modifications” to the proposed route because of “oversights in the routing process.”
In a March 4 filing, after initially saying Appalachian Power and Wheeling Power customers wouldn’t face rate increases, NextEra indicated the project would result in annual increases of 0.1% for average residential customers of those utilities each year from 2032 through 2036, corresponding with bill hikes ranging from $0.17 to $0.18 in that span for use of 1,000 kilowatt-hours per month.
Residential customers of Appalachian Power and Wheeling Power also would see estimated rate increases ranging from 0.01% to 0.07% from 2026 through 2031, per the filing.
Mon Power and Potomac Edison residential customers would take a greater hit, with estimated increases ranging from $1.02 to $1.12 (0.74% to 0.81%) per month for 1,000 kilowatt-hours from 2032 through 2036 after changes ranging from $0.14 (0.1%) to $0.84 (0.61%) annually from 2026 through 2031.
Route revisions proposed by NextEra six months after its Jan. 30 application, Egnatoff testified, have left him concerned the company may find it necessary to make further revisions even later in the process and hasn’t kept the PSC and its staff informed regarding issues in the case.
Egnatoff advised that if the PSC does approve the project, it should, in part:
PSC staff says field visits revealed wide-ranging concerns
Egnatoff testified that his visits to roughly 80 landowners and their properties within the project study area revealed concern that property located near high-voltage transmission lines usually is worth less than comparable property that is not.
Many impacted property owners described detailed, long-term plans for properties, including personal residences, residential and business development, conservation and agriculture, that they had stopped when notice of the MARL project was delivered, Egnatoff reported.
“These owners have already been impacted by the MARL Project, whether the Commission approves it or not,” Egnatoff testified, adding that one family stopped construction on a residence that was near completion upon notice that the structure would be within the line’s right-of-way.
Egnatoff stated that few contacted landowners described positive interactions with the employees of NextEra and its contractors. Landowners cited high-pressure tactics, repeated unsolicited contacts and misrepresentation of the process, such as implying that the MARL project is “inevitable,” Egnatoff said.
Distances of 80 feet or less from the project right-of-way are “a common occurrence,” Egnatoff testified, saying that one home is 35 feet from the right-of-way, placing both that person and their next-door neighbor entirely within the siting corridor, and that another home’s north wing is less than 20 feet from the edge of the right-of-way.
In what Egnatoff said was “a particularly striking case,” the line would pass roughly 150 feet north of a home, then turn and pass about 90 feet to the east of the same home, surrounding it on two sides.
Egnatoff observed that as of Sept. 4, there had been 7,902 public comments filed with the PSC in protest of MARL and just 153 in support — a 98.1% share of comments against the project.
Egnatoff noted examples of power providers revising use forecasts downward after applying further requirements to prospective data center customers, including AEP Ohio cutting a significant amount of consumption from its forecast after implementing a tariff that shifted more interconnection costs onto data center customers.
There is risk, Egnatoff warned, of “expensive and unnecessary overbuild of transmission resources to serve load that may never materialize.”
‘If and when this bubble bursts … ‘
NextEra has committed to an in-service date of Dec. 31, 2031, adding in a filing that it’s working to accelerate the in-service date to December 2029 or earlier to meet PJM grid reliability needs.
Kunkel recommended denial of NextEra’s application, estimating that through 2046, West Virginia ratepayers would pay over $210 million toward project construction and operation.
The majority of that cost, nearly $200 million, would fall on customers of Mon Power and Potomac Edison, Kunkel estimated, adding that of the total cost, nearly $90 million would be covered by West Virginia residential ratepayers.
Kunkel testified that what she called “aggressive long-term forecasts of data center demand” from PJM, including growth into the 2040s, may not materialize to the extent projected due to “fundamental weaknesses in the artificial intelligence business model.”
Kunkel cited competition with emerging Chinese models holding subscription prices below levels covering the actual costs of building and training AI models, growing and possibly understated depreciation expenses, and investors and analysts increasingly raising concern about an AI “bubble.”
“If and when this bubble bursts, it will likely lead to bankruptcies and a cooling off of investment in the sector — and very likely less operational data center capacity than currently forecast,” Kunkel testified. “This may place ratepayers in PJM in the situation of having shouldered the cost of transmission investments based on expected data center demand that failed to fully materialize.”
Hampshire Co. leader reports deeply negative feedback
In testimony filed Tuesday, Hampshire County Commissioner Logan Mantz reported that of 452 responses to a community survey he helped draft to give residents and landowners a way to give feedback on MARL, 430, or 95.1%, disagreed or strongly disagreed that MARL would be in the best interest of West Virginia and its citizens.
In other testimony filed Tuesday, Rebecca Keiver of High View, Hampshire County, reported that NextEra’s proposed line would run parallel to a high-voltage line already crossing part of her 29-acre property that splits off a separate branch, meaning that MARL moving forward would result in the burden of three separate power-line impacts taking close to half of her total usable land.
Keiver said she invested more than $700,000 into clearing, building a pond and new home, adding RV pads and other amenities as she plans a multigenerational family compound with riverfront homes for her son and other family members.
“Several generations of my family are planning to raise children on this land, which is a big part of why I am raising these concerns now,” Keiver testified.
Mary Margaret Major of Points, Hampshire County, said in testimony filed Tuesday that maps filed by NextEra show a siting corridor that extends onto or immediately next to the 28-acre property on which she and her husband began construction on their “forever home” in 2017, moving from Cecil County, Maryland, in pursuit of a small farm “where we could live a quiet, peaceful life.”
The siting corridor extends onto her property up to their barn, including within it their chicken coop and shed, Major testified.
Major noted that because the final center line, tower locations and exact right-of-way boundaries aren’t finalized, she can’t determine the full extent of impacts that could occur on or near her property.
“The project would fundamentally alter the use and enjoyment of our property, threaten agricultural activities we have spent years developing, and undermine the peaceful rural character that led us to build our forever home in Hampshire County,” Major testified. “These impacts are not temporary; they would be permanent.”
Tags:
- apco
- Appalachian Power
- cathy kunkel
- chris beam
- christian beam
- daniel egnatoff
- Environment
- FirstEnergy
- hampshire county
- kaitlin mccormick
- logan mantz
- marl
- midatlantic resiliency link project
- mon power
- NextEra
- NextEra Energy
- patrick morrisey
- potomac edison
- PSC
- psc staff
- wati
- west virginians against transmission injustice
- wheeling power
- wpco
- WV PSC