After the Chino Planning Commission over the summer denied development plans for a controversial battery energy storage system (BESS) facility near a beloved city park, the City Council on Tuesday, Sept. 15, reversed that ruling and approved energy developer AYPA Power’s request for a development agreement for the project.

The City Council’s 4-1 approval of a special conditional use permit, site approval and development agreement makes the Dirac BESS Project the city’s first major BESS facility and among the largest in California.

The Planning Commission on July 15 rejected the plan on a 4-3 vote. AYPA’s appeal was opposed Tuesday by Mayor Pro Tem Curtis Burton, who said the project “sounds good on paper.”

“Realistically speaking, if one of those containers starts on fire, hopefully the systems don’t fail and somebody is alerted,” Burton said, echoing concern from half of the packed chamber opposing the project. “This is the best location for this project … but do we want to be the test site for something like this to come to our city?”

Support for the 400-megawatt Dirac Project, totaling 13.89 acres north of a Southern California Edison substation and 900 feet from Ayala Park and residential areas along Edison Avenue, came from labor unions and clean energy supporters. According to city documents, the BESS would have enough to power about 400,000 single-family homes with about eight hours of electricity, addressing rolling blackout concerns and acting in line with state energy goals.

In support of the project, Councilmember Karen Comstock said “there are risks to this project, but there are benefits.”

Comstock alluded to historic heat affecting Inland Empire communities like Chino, echoing Gov. Gavin Newsom’s August statement: “extreme heat earlier, longer, and more intensely than ever before.”

“This project deserves the public scrutiny tonight,” Comstock said, also emphasizing that following AYPA Power’s earlier July rejection by the Planning Commission, officials met with staff in continuation of their 18-month collaboration in compliance with Chino’s zoning plan, policies and requirements to further address existing concerns.

Given residents’ and the planning commission’s concerns, staff requested additional safety conditions: installation and maintaining of continuous, real-time carbon monoxide detection and air monitoring; annual, third-party emergency response training for fire district personnel; requiring written approval from the fire district should AYPA use an alternative battery chemistry; and the emergency response plan to be coordinated and distributed to the fire district and Chino Police Department.

Additionally, Chino Valley Fire Chief Dave Williams said: “We feel very well-trained.”

A city staff report, prepared by Senior Planner Kim Le, favored granting AYPA Power the necessary documents and development agreement, and included 14 letters supporting the Dirac BESS from labor companies, green-energy groups and the Governor’s Office of Business and Economic Development.

“Local, state and national codes — all of them are enforced over the life of this project,” AYPA Senior Vice President of Development Aron Branum said, adding that should the codes not be enforced, the city, fire district and other authorities can stop project operations. “21 people spoke against this project in July. Not one concern they raised goes unaddressed in the materials before you tonight.”

According to Branum, the Dirac BESS cleared the city’s environmental review safety thresholds with a “wide margin,” and that AYPA Power has no incident rate for projects that are the same as the Dirac BESS Project.

Prior to Tuesday’s appeal hearing, the Dirac Project drew worries surrounding the development.

Earlier in the month, an online petition opposing the project had over 200 signatures; it is now over 500.

Many of the comments Tuesday, including two written opposition letters in the staff report from residents concerned for property and communities near the proposed site, were concerned about potential thermal runaway – when lithium-ion batteries become uncontrollable in a self-heating state, leading to smoke and fire – and proximity to residential communities, among other concerns.

“The issue is whether the specific 400-megawatt facility at this specific location has demonstrated, through independently verifiable evidence, that its foreseeable fire, environmental, emergency response, noise, and long-term financial risks are adequately mitigated,” one speaker said. “Just because we can, doesn’t mean we should be the first city to put 400 megawatts next to our residents.”

Within its appeal document, AYPA Power representative Geoff Forner disputed these concerns, citing that “Dirac BESS is materially different” to other problematic BESS projects including the Moss Landing project that burned in January 2025. That was at a 300-megawatt facility in Monterey County’s Moss Landing.

“The Planning Commission’s denial is not supported by the record,” Forner wrote.

The ordinance approving the development agreement will go into effect Oct. 6.