Latvia’s transport ministry says building the Rail Baltica main line in Latvia by 2030 is technically impossible, in a statement on the cabinet’s 1 October review of the project.
Rail Baltica main line construction near Iecava. Photo: EDZL.
The government examined a report from the Ministry of Transport on the strategy for taking Rail Baltica forward in Latvia. The report sets out several ways of completing the project, what each would cost and how much extra state budget money they would require. Transport Minister Rihards Kozlovskis said the cabinet had been given a full picture of the project for the first time, and that its costs now need a fundamental review.
Consultants find the current approach unworkable
Under a cabinet decision of 10 June 2025, the international consultancy Alvarez & Marsal Infrastructure & Capital Projects was brought in to carry out an in-depth review of the project’s management, finances, economics, technology and legal set-up. The consultants concluded that, given current capital cost estimates, the expected funding gap and the timetable, Rail Baltica cannot be delivered in Latvia if the existing approach is kept.
According to the ministry, more money alone would not fix this. The consultants call for structural changes as well, including in how the project is governed, planned and kept within budget.
Kozlovskis said the Baltic rail system should still be linked to the European network, because such a corridor could become an important part of military mobility and civil security in the current geopolitical situation. He added that this has to happen at a reasonable cost, that the project must be fundamentally reworked to make it deliverable, and that its timing and funding have to be agreed with the European Commission.
Cabinet orders a minimum viable configuration
Following the consultants’ advice, the government decided that a minimum viable configuration (MVC) should be drawn up. It is meant to define the smallest scope and set of infrastructure needed for the Rail Baltica main line to function. By the end of 2026, the ministry will run a market survey to hire an external, independent consultant for this work and report back to the cabinet on the results and on the funding the MVC would need.
Until the MVC is ready and further decisions are taken, activities already under way will continue within the funding already allocated. No new financial or contractual commitments may be made for the project without cabinet permission. State budget funding will be considered once the MVC is complete, as part of preparing that year’s budget bill.
Also by the end of 2026, the State Chancellery and the transport ministry are to propose a governance model for the project under cabinet supervision. The ministry will separately report on the state funding needed to maintain and conserve Rail Baltica infrastructure that has already been built.
Latvia keeps its €10 billion request to the EU
In talks with EU institutions, Latvia’s foreign and transport ministries will continue to defend the country’s approved position: €10 billion of EU co-financing for the Baltic states to build Rail Baltica, at a rate of 85%, in the EU’s 2028–2034 long-term budget.
The same sum is at the centre of a common declaration approved by the heads of government of Estonia, Latvia and Lithuania on 22 September 2026. In it, the three states undertake to have the main line operating during the next Multiannual Financial Framework (MFF), while saying they will keep aiming to build as near as possible to the timetable now fixed in Commission Implementing Decision (EU) 2025/1332.
That decision, adopted on 9 July 2025, makes 31 December 2030 the end of the project’s first phase. By that date, electrified standard-gauge infrastructure is due to be finished on the priority route from Tallinn to Warsaw via Pärnu, Salaspils, Panevėžys and Kaunas, and the European Rail Traffic Management System (ERTMS) is due to be deployed. The declaration also states that the first phase can only be delivered if the project achieves meaningful cost reduction.
Rail Baltica first-phase deadlines in Commission Implementing Decision (EU) 2025/1332
Section
Milestone
Deadline
Tallinn–Pärnu
Railway infrastructure finished
31 December 2028
Pärnu–Estonian-Latvian border
Railway infrastructure finished
31 December 2028
Estonian-Latvian border–Salaspils
Railway infrastructure finished
31 December 2029
Salaspils–Latvian-Lithuanian border
Railway infrastructure finished
Mid-2029
Latvian-Lithuanian border–Panevėžys
Railway infrastructure works under way
Mid-2029
Panevėžys–Kaunas
Track superstructure finished
Mid-2029
Lithuanian-Polish border–Marijampolė
Railway infrastructure finished
31 December 2028
Marijampolė–Kaunas
Railway infrastructure finished
31 December 2029
Warsaw–Ełk
Upgrade works finished
31 December 2029
Ełk–Lithuanian-Polish border
Section finished
31 December 2030
Whole Tallinn–Warsaw route
Electrified standard-gauge line and ERTMS in place
31 December 2030
The 2025 decision puts every first-phase deadline on or before 31 December 2030. In the 22 September 2026 declaration, the three governments commit to opening the main line within the next MFF while keeping construction as near as possible to these dates. Source: Commission Implementing Decision (EU) 2025/1332, adopted on 9 July 2025.
Rail Baltica cost estimate and the proposed EU transport fund
RB Rail AS, the project’s joint venture, put the cost of the first phase at €15.3 billion in 2022 prices in an updated cost-benefit analysis released in June 2024. That estimate assumed an operational line across the three Baltic states connected to Poland by 2030, at roughly €26 million per kilometre. The company said that EU financing beyond the sources already secured would largely depend on negotiations over the next EU budget.
For that budget, the European Commission proposed a Connecting Europe Facility of €81.4 billion for 2028–2034, including €51.5 billion for transport and military mobility. The €10 billion sought by the Baltic states corresponds to just under a fifth of that proposed transport and military mobility envelope.