PKP PLK’s Jastrzębie-Zdrój rail tender, launched October 26, seeks a contractor to rebuild the rail link that would return passenger trains to the city for the first time since 2001.

Tracks and platforms at Żory station, with a freight locomotive on the leftTracks, platforms and a freight train at Żory station. Photo: PLK SA.

The procedure covers the first stage of the Kolej Plus project linking Jastrzębie-Zdrój, a city of about 80,000 in southern Poland, with Katowice. It concerns line 159 between Żory, Pawłowice Śląskie and Jastrzębie-Zdrój, and contractors have until December 4, 2026, to submit bids. PKP Polskie Linie Kolejowe (PKP PLK), which announced the tender, describes Jastrzębie-Zdrój as the largest city in Poland without access to rail.

What the line 159 contract covers

The core of the job is rebuilding the 8-kilometer section from Pawłowice Śląskie to Jastrzębie-Zdrój. The line will be electrified and built for speeds of up to 120 km/h. The plans include a Jastrzębie-Zdrój station and four stops, Jastrzębie-Zdrój os. Barbary, Jastrzębie-Zdrój Bzie, Żory Wschodnie and Żory Baranowice, as well as work at Pawłowice Śląskie station. Platforms will be accessible to passengers with reduced mobility.

The contract notice divides the work into two packages. The first is a build-only package covering track and subgrade, drainage, the overhead line and its power supply, structures, platforms and crossings. The second is a design-and-build package for signaling and telecommunications. PKP PLK has also listed options for road structures with access to the platforms at Żory Baranowice and Żory Wschodnie, a road with a parking lot in Pawłowice, and changes to signaling interfaces.

The city of Jastrzębie-Zdrój reported the contract’s estimated value as 270 million zloty, excluding VAT. The project is funded from the state budget under Kolej Plus.

Construction schedule and mining ground

The notice gives the winning bidder 24 months from contract signing to finish the basic scope, followed by up to six months to deliver the authorizations needed to place the new subsystems into service. PKP PLK expects construction to take place in 2027-2030.

Speaking at the launch in Żory, PKP PLK board member Marcin Mochocki described the plan of two months of mobilization followed by 20 months of construction as very ambitious. He said the end of construction would not automatically mean regular trains, because rail authorizations still have to be obtained, in part because a stretch of the route will follow a new alignment. He also pointed to difficult ground: the route crosses former mining areas and requires a complex structure over a pond formed by mining subsidence.

Katowice service and the Orzesze–Żory section

PKP PLK says that once the line is rebuilt, residents will be able to travel by train to Pawłowice, Żory, Rybnik, Pszczyna and Katowice. Deputy Infrastructure Minister Piotr Malepszak said the aim is a journey to Katowice of up to 60 minutes. Earlier plans assumed 12 pairs of trains a day on the Jastrzębie-Zdrój–Żory–Katowice route. The city notes that the actual timetable offer still has to be agreed.

The tender does not cover the full project. The decision on environmental conditions issued in February 2026 by the Regional Director for Environmental Protection in Katowice covers three sections of line 159, including Orzesze–Żory. In a June 2026 reply to lawmakers, the Ministry of Infrastructure said it was considering a staged approach. Under that option, works on Żory–Pawłowice–Jastrzębie-Zdrój would be tendered in 2026, while the Orzesze–Żory section would depend largely on further decisions about the CPK rail investment and on available funding.

Line 159 sections in the environmental decision and the October 2026 tender

Section
Location on line 159 (environmental decision)
Planned passenger stops and stations
Included in the October 2026 tender

Orzesze–Żory
km -0+005 to 14+087
Orzesze Zawada, Palowice
No. The Ministry of Infrastructure said in June 2026 that this section would depend largely on decisions about the CPK rail investment and on available funding.

Żory–Pawłowice Śląskie
km 15+746 to 18+850
Żory Wschodnie (about km 15+947), Żory Baranowice (about km 17+862)
Yes

Pawłowice Śląskie–Jastrzębie-Zdrój
km 26+170 to 34+796
Jastrzębie-Zdrój Bzie (about km 29+925), Jastrzębie-Zdrój os. Barbary (about km 33+340), two-track Jastrzębie-Zdrój station
Yes

Notes and sources
Two of the three line 159 sections are in the tender, and the Orzesze–Żory section is not. Kilometer points and stops come from the annex to the February 2026 decision on environmental conditions and are approximate where marked. They do not describe the exact limits of the tendered works. Tender coverage is based on PKP PLK’s tender announcement and the Ministry of Infrastructure reply of June 2026.

Cost and travel-time estimates for the Katowice link

Earlier replies from the Ministry of Infrastructure to lawmakers set out how the estimates moved. In June 2025, the ministry said projected costs had risen because of land acquisition, specialist geotechnical work in areas affected by mining damage and a larger scope than in the application documents. In the same reply, it put the planned Kolej Plus travel time from Katowice to Jastrzębie-Zdrój at about 1 hour 12 minutes for regional trains stopping at every station. In December 2025, the ministry said about 475 million zloty had been secured under an agreement between PKP PLK and the Silesian Voivodeship, with local governments covering 15% of eligible costs, while the total cost was estimated at about 875 million zloty. It added that the Jastrzębie-Zdrój–Pawłowice Śląskie section should be built first.