Many advanced reactors need a richer uranium fuel the U.S. barely produces. New enrichment capacity is due by 2029, a year after waivers for Russian imports expire.

The second U.S. company with a federal contract to make high-assay reactor fuel filed its first license application on Sept. 28, and the filing does not yet cover that fuel. For procurement teams negotiating for small modular reactor (SMR) power, the timeline behind it is the one their reactors will run on.

General Matter submitted the more than 1,000-page application to the Nuclear Regulatory Commission (NRC) for an enrichment plant in Paducah, Kentucky, covering conventional low-enriched uranium (LEU). The company says it will add high-assay fuel through an amendment next year and plans to enrich “at commercial scale by the end of the decade.” It has asked for an accelerated review, and it walked NRC staff through the application at a closed meeting on Oct. 14 as part of the agency’s acceptance review.

The fuel is high-assay low-enriched uranium (HALEU), enriched to between 5% and 20%, well above the roughly 5% used in today’s large reactors. Only one U.S. plant has produced it at any scale. The Department of Energy (DOE) says the country has limited commercial supplies of HALEU enrichment services and treats that gap as a constraint on deploying advanced reactors.

One Ohio Plant, a Few Tons of Output

Centrus Energy finished its federal demonstration contract at Piketon, Ohio, in June with more than 1,900 kilograms of HALEU produced in total, according to a company release filed with securities regulators. On July 1 it finalized a $900 million DOE contract, expandable to $1.07 billion, to build commercial capacity there. The first new capacity is expected online by 2029, with an initial build-out of 12 metric tons of HALEU a year. Centrus said the pace of expansion depends on customer demand and capital.

“Today’s announcement marks another milestone in our expansion,” said Amir Vexler, Centrus president and CEO. Until the new centrifuges arrive, the company plans to run its existing cascade commercially to serve near-term customers. The plant has been producing HALEU in Ohio since 2023.

General Matter’s filing traces back to January, when DOE awarded $2.7 billion in enrichment contracts, including $900 million each to Centrus’s operating subsidiary and to General Matter for HALEU, and $900 million to Orano for conventional low-enriched uranium (LEU). The money is released against milestones over 10 years.

Developers Are Prepaying for Their Place in Line

Reactor companies have started paying in advance. On Aug. 6, Centrus signed an enrichment contract with X-energy covering both LEU and HALEU for X-energy’s first Xe-100 reactors and its TRISO-X fuel plant, with X-energy making prepayments to support Centrus’s expansion. Vexler called it an agreement that “validates Centrus as the go-to, de-risked supplier of HALEU.” X-energy has also signed an enrichment agreement with General Matter, its chief executive told investors in August, a bet on a plant that has only now entered NRC review.

For a corporate buyer, those prepayments are a useful signal. A developer that has secured enrichment and fabrication has removed one dependency from its schedule. One still waiting on government allocations has not. DOE’s HALEU Availability Program has made conditional allocations from federal stockpiles in three rounds since April 2025, most recently to NASA and Radiant Industries on July 23. Those allocations cover demonstration units and early cores, not decades of commercial refueling.

The Russian Backstop Has an End Date

Russia has long been the main commercial source of HALEU. The Prohibiting Russian Uranium Imports Act, signed in May 2024, bans Russian enriched uranium and lets DOE grant waivers. Any waiver must end no later than Jan. 1, 2028. That leaves a gap of about a year before Centrus’s new capacity is scheduled to arrive.

GE Vernova Hitachi’s BWRX-300, the design under construction in Ontario, sidesteps the problem because it runs on conventional LEU, the same fuel chain that serves today’s boiling water reactors. Fuel fabricators are also expanding, with approval for higher-enrichment fuel manufacturing and new entrants such as Standard Nuclear in DOE’s fuel pilot program.

Competition for the First Tons

The race among suppliers will shape which reactors get fuel first. Centrus has a working cascade and a 2029 target. General Matter holds the same size DOE award and is aiming for production by 2030, pending a license it has only just requested. Developers that prepay can lock in early volumes, while those that wait may find the first years of output already spoken for. The next markers are the NRC’s decision on whether to accept General Matter’s application for review, the company’s HALEU amendment in 2027 and the Russian waiver deadline in January 2028.