TALLAHASSEE Fla. — The Florida Public Service Commission unanimously rejected Duke Energy Florida’s proposal for handling costs tied to large load customers, including data centers, saying the plan did not meet Florida law.
The decision drew positive feedback from the CLEO Institute, a Florida-based nonprofit dedicated to climate action.
“So for anybody that wants to stand up for affordable electricity and to push back against this energy burden that so many Floridians feel, this is a win,” said Raymer Maguire, vice president of campaigns for the CLEO Institute.
In a news release, the Florida Public Service Commission said Duke’s proposal did not meet requirements under Senate Bill 484. The law says utilities must ensure data centers take on the full cost of their electric service and do not pass those costs on to average customers.
“So this is the first time where we’ve really seen that new law challenged,” Maguire said.
Duke Energy Florida said in a statement that it appreciates the commission’s careful review.
“We remain focused on getting this right for Florida by supporting economic growth and new jobs while protecting customers and ensuring that data centers pay their full cost of service,” the company said in a statement.
Senate Bill 484 went into effect July 1 as data centers have become an increasingly contentious topic.
Jonathan Lewallen, associate professor of political science at the University of Tampa, said opposition to data centers has grown as lawmakers have sought to shift the burden data centers can bring away from the public and back to the data centers.
“The state lawmakers sort of interest, or at least they perceive it’s in their interest, to really publicize how they are treating data centers in a way that is very visible,” Lewallen said.
Maguire said the CLEO Institute supports utilities that are environmentally friendly.
“As we bring on these new data centers in Florida, they’re very rarely being powered by renewable energy like solar,” Maguire said. “And instead it’s just resulting in even more methane gas being burned.”
Tampa Electric recently filed its own proposal for handling data center costs. That plan is still waiting for review.
Duke Energy Florida could file another petition for the Public Service Commission to review.