The U.S. Energy Dept. closed a $480-million loan Nov. 10 to finance The Woodlands, Texas-based Arena Energy’s rehabilitation and expansion of 22 offshore oil and gas platforms off Louisiana, a brownfield redevelopment called Project Elkhorn that includes restarting idled facilities and adding pipeline infrastructure.

Described as the agency’s first closed loan for domestic oil and natural gas production infrastructure, it will support work on existing platforms in the Southern Eugene Island area of the Gulf, where Arena says it will refurbish, retool and repower facilities, increase production and water-handling capacity and connect future production through new natural gas pipeline infrastructure.

The project is expected to support about 2,400 construction jobs and, at peak output, add up to 38,600 barrels per day of oil production and 77 million cu ft per day of natural gas production, according to DOE. Arena currently produces about 30,000 barrels per day offshore.

]]>

Arena says it will execute Project Elkhorn with affiliated companies White Fleet Drilling and Rosefield Pipeline.

A development plan that company unit Arena Offshore LP submitted in February to the U.S. Bureau of Ocean Energy Management, a U.S. Interior Dept. unit, calls for returning an existing platform in Eugene Island Block 353 to active use and drilling two wells from open slots in the structure. The filing says Chevron installed the two-deck, 20-well-slot Platform D in 1984 in about 296 ft of water.

“The Southern Eugene Island area is one of the most prolific oil-producing regions in American history, and its infrastructure still has decades of productive life ahead,” Arena founder and CEO Mike Minarovic said in a statement. “Reinvesting in existing infrastructure is one of the most efficient ways to add American energy production, support skilled jobs, and generate value.”

The plan identifies either White Fleet Drilling’s WFD 400 or WFD 450 jack-up rig for the two wells. Separately, Arena says White Fleet deployed the WFD 450 to active drilling operations in Southern Eugene Island in late March after completing a $65-million acquisition and refurbishment program. The rig had previously been cold-stacked for seven years. White Fleet rates it for water depths of up to 400 ft and drilling depths of 30,000 ft.

]]>

Looking for quick answers on construction and engineering topics?
Try Ask ENR, our new smart AI search tool.

Ask ENR →

For the two wells, the plan calls for hydraulically hammering 24-in. to 48-in. drive pipe about 200 ft to 300 ft below the mudline. The DOE environmental review excludes future development drilling from the financed scope.

The bureau plan separately describes infrastructure proposed for Platform D. The existing platform would receive a well-test system consisting of a manifold, test separator and fuel and instrument gas system. Liquids would leave the facility through a proposed 10-in. right-of-way pipeline connected to existing pipeline systems, while gas would move through a proposed 8-in. right-of-way pipeline.

The $480-million financing is structured in five tranches extending through 2030. A DOE environmental review says future development drilling, routine operations, eventual decommissioning and separately financed onshore engineering and fabrication are outside the defined financed scope.