Musk warned that AI data center delays could create a 2027 cash gap of hundreds of billions of dollars.
Dan Ives sees SpaceX becoming the biggest AI hyperscaler as demand outpaces planned capacity.
Tesla cut AI4.5 memory by 25% and Musk said AI5 will go to Optimus.
A day after investors lined up to finance $44 billion of AI equipment for SpaceX (SPCX), CEO Elon Musk warned that even a few months of data center delays could leave the industry needing hundreds of billions more.
SPCX shares fell 8% to $127.79 on Friday, bringing their weekly decline to 8%, the steepest this month.
Musk Sees 2027 Funding Gap For AI Companies
Musk warned on Saturday that AI companies could face a cash crunch in 2027 as they wait for costly chips to start earning revenue. He was responding to AI researcher Francois Chollet, who said graphics processors were scarce and getting more expensive to rent. Even after the chips arrive, Musk said, operators still have to power and cool them and get them running reliably enough to bill customers.
“The cash shortage is also going to be nuts next year,” Musk said. “Even cumulative industry delays of a few months between paying for compute and getting it reliable enough to generate revenue will mean hundreds of billions of incremental dollars just for working capital. Where will that come from?”
How Funding Pressure Gives SpaceX More Pricing Power
“I own $SPCX and believe it may be the largest AI hyperscaler in the not too distant future,” Futurum CEO Daniel Newman said. He also owns specialist cloud providers Iren (IREN) and CoreWeave (CRWV). If smaller providers struggle to finance their next data center, he said, SpaceX faces fewer rivals bidding for customers and gains more room to set prices.
“The conditions Elon speaks to are real, but creating a massive spiral for smaller AI clouds is definitely in his best interest. It’s good use of the platform and a good chess move. But it isn’t just some altruistic advice for investors,” Newman said.
Iren had the funding in place and the timing still slipped. Its first Horizon data center went live for Microsoft, and quarterly AI cloud revenue nearly tripled to $200 million. But a customer’s design change and suppliers’ schedules pushed back Iren’s target for bringing more than $4 billion in annualized contracted revenue online. The company now expects to reach that level in January, possibly as late as the end of February, after initially targeting year-end.