0% operational, 10% under construction (soon ~18%, financed by NRRP) & 90% in different stages of projects.
**A10 Motorway, Sebes – Turda, 70km**
100% Operational
**A11 Motorway, Arad – Oradea, 135km**
Will be an Expressway on most its length.
3% operational, 14% under construction & 83% planned (soon to be auctioned).
**A13 Motorway, Sibiu – Brasov – Bacau, 300km**
0% operational, 12% under construction & 88% planned.
**DEx4 Expressway, Turda – Dej, 70km**
0% operational, 7% under construction, 93% planned
**DEx6 Expressway, Braila-Galati, 12.28km**
100% under construction
**DEx12 Expressway, Craiova-Pitesti, 121.35km**
33% operational & 67% under construction.
~300km from A7, ~13km from A1 and ~40km from A3 are financed by the PNRR (NRRP) funds, thank you EU and former minister Drula for this.
How is it it works with 130km.ro
When do they add stuff to the map? Like for example the belt way in Satu Mare is supposed to be part of a road leading over Baia Mare and down towards Turda.
Are there any plans for the section to Serbia?
Again these maps, mixing hope and reality.
You should do a gif with the map at various points in time, also available on 130km.ro. Would better emphasize the recent progress.
7 comments
In the image we see the Romanian motorway and expressway map and current status of ongoing projects.
Source: 130km.ro
Opened – 1008km
Under Construction – 768km
Planned – too many
Details about the Current and relevant planned Motorways
**A0 Motorway, Bucharest bypass, 100.7km**
0% operational, 100% under construction.
**A1 Motorway, Bucharest – Nadlac (HU border), 578.48km**
79% operational, 21% under construction.
**A2 Motorway, Bucharest – Constanta, 202.79km**
100% operational
**A3 Motorway, Bucharest – Borș, 438km**
42% operational, 14% under construction, 44% planned/no financing.
**A4 Motorway, Constanta Bypass, 21.78km**
100% operational
**A6 Motoroway, Lugoj – Calafat – Bucharest**
Just 10.5km operational, rest is being planned or has no financing.
**A7 Motorway, Ploiesti – Siret (Ukraine Border, 437km**
4% Operational, 70% under construction (NRRP) & 26% soon to be auctioned for construction
**A8 Motorway, Tg. Mures – Ungheni (MD border), 310km**
0% operational, 10% under construction (soon ~18%, financed by NRRP) & 90% in different stages of projects.
**A10 Motorway, Sebes – Turda, 70km**
100% Operational
**A11 Motorway, Arad – Oradea, 135km**
Will be an Expressway on most its length.
3% operational, 14% under construction & 83% planned (soon to be auctioned).
**A13 Motorway, Sibiu – Brasov – Bacau, 300km**
0% operational, 12% under construction & 88% planned.
**DEx4 Expressway, Turda – Dej, 70km**
0% operational, 7% under construction, 93% planned
**DEx6 Expressway, Braila-Galati, 12.28km**
100% under construction
**DEx12 Expressway, Craiova-Pitesti, 121.35km**
33% operational & 67% under construction.
~300km from A7, ~13km from A1 and ~40km from A3 are financed by the PNRR (NRRP) funds, thank you EU and former minister Drula for this.
How is it it works with 130km.ro
When do they add stuff to the map? Like for example the belt way in Satu Mare is supposed to be part of a road leading over Baia Mare and down towards Turda.
Are there any plans for the section to Serbia?
Again these maps, mixing hope and reality.
You should do a gif with the map at various points in time, also available on 130km.ro. Would better emphasize the recent progress.
Why no connection to Bulgaria?
So the Bucharest ring should be done by 2025, eh?