Tesla CEO Elon Musk on Thursday posted the most detailed expansion timeline yet for his artificial intelligence infrastructure project Colossus 2 on social media platform X, targeting a more than doubling of Nvidia chips at the Memphis, Tennessee data center by the end of this year.

Musk said Colossus 2 currently houses 110,000 Nvidia GB200 chips and 440,000 GB300 chips, totaling 550,000 units. According to the plan he outlined, 220,000 GB300 chips will come online next week, with another 220,000 added in November. If all goes smoothly, an additional 220,000 could be deployed in late December. At that point, the GB300 chip count would reach 1.1 million, and combined with the existing GB200 inventory, the total would approach 1.21 million chips.

This means that even under a conservative scenario, Colossus 2’s Nvidia chip count would rise from the current 550,000 to 990,000 by year-end—an increase of roughly 80%. If the final December batch arrives on schedule, the growth would exceed 100%.

xAI had previously set a goal of equipping the Memphis facility with 1 million graphics processing units (GPUs) by 2026. Based on the figures Musk disclosed, that target could be reached ahead of schedule on GB300 chips alone.

Behind the Expansion: Surging Compute Demand

Musk has long positioned Colossus as “the world’s largest AI supercomputer.” Colossus 1 was built in 2024, initially to train xAI’s flagship AI model, Grok. However, the facility’s scope has expanded considerably since then.

In February 2026, SpaceX completed its acquisition of xAI in an all-stock transaction, making xAI a business unit under SpaceX. Since then, SpaceX has aggressively marketed Colossus’s compute capacity to external parties. In May, SpaceX signed a cloud services agreement with frontier AI model company Anthropic, which will use compute capacity from both Colossus and Colossus 2. SpaceX has also reached compute partnership arrangements with Google parent Alphabet, Reflection AI, and other players.

From in-house Grok training to external compute leasing, Colossus’s evolving role reflects the intense demand for high-performance computing resources across the AI industry. Musk is rapidly scaling up compute capacity to secure a critical infrastructure position in this wave.

Notably, Musk did not address whether Colossus 2 has sufficient power supply and immediately available capacity to support the operation of the new chips. Data center expansions typically require simultaneous upgrades to power, cooling, and networking infrastructure—all potential bottlenecks in actual deployment.

What It Means for Nvidia

Colossus 2’s expansion plan is a significant positive for Nvidia. If 660,000 GB300 chips are added by year-end as planned, a single customer would have purchased a substantial volume of chips within roughly three months. The GB300 is part of Nvidia’s Blackwell generation, and this large-scale procurement further validates the robust market demand for the Blackwell series.

Nvidia’s stock has been supported throughout the year by expanding capital expenditures from major tech companies and AI startups. Colossus 2’s expansion timeline provides the market with another concrete indicator of order visibility.