The industry’s most important number is not how fast your chip can theoretically compute. It is how much useful work actually happens when a cluster of 100,000 accelerators is running real workloads and failing constantly — sometimes multiple times an hour. That is the argument at the core of a conversation with Amin Vahdat, Google’s AI infrastructure chief, speaking on the Training Data podcast with host Sonya Huang.
The term he uses is “goodput.” Throughput, he explains, is the work you do. Goodput is the work that actually advances the answer. His analogy: solving a problem on paper, reaching step four, discovering a mistake, and restarting from step one. You are still doing work — that is throughput. But the time to the final answer is what matters. Failures, recovery, and anything that interrupts a job all degrade goodput.
At Google’s current scale, this is not an academic concern. A 100,000-accelerator deployment — each chip a package of chiplets, HBM, network connections, and sometimes co-packaged optics — will see failures multiple times a day. Vahdat is blunt about why there is no easy fix. “If there were a common failure reason, we’d have figured it out and fixed it,” he said. “It is a long tail of constant discovery.”
The breakdown is unglamorous: new products introduce new failure modes, often network-related at very high connection speeds, sometimes hardware failures, and frequently software — compiler bugs, runtime bugs, OS issues. Perfect hardware with a compiler bug still produces bad end-to-end performance. Finding these problems is, in his words, “finding a needle in the haystack continuously.”
The TPU split: when inference gets big enough to justify a second chip
The most concrete decision Vahdat describes is why Google split its 2026 TPU generation into two chips — the TPU 8i for inference and the TPU 8t for training. Roughly two years before the episode, his team confronted the question of whether 2026 should have one chip or two. The deciding calculus was market size. If inference were projected at 2% or 5% of the market, even a 2x-faster specialized chip would not justify a separate program. By 2026, Google projected inference and serving at 30–60% of the chip’s lifetime market, which made specialization sensible.
Two constraints shaped the outcome. First, both chips retain some capability on the other’s workload — otherwise Google would have to predict, years in advance, exactly how much of each it needed. Second, the workload has to be durable. A workload that is huge for three months but gone after that offers “a really narrow window to intercept it.”
Decision factorThreshold Vahdat describesWorkload share of market2–5% does not justify a specialized program; 30–60% doesWorkload durabilityMust persist across the ~6-year hardware lifetimeCross-compatibilityBoth chips must retain some capability on the other’s workloadProjected winMust be quantifiable before committing to specialization
Huang pushes further: why not burn the transformer architecture directly into silicon? Vahdat’s answer reveals the limit of specialization. Transformers reduce to vector and matrix multiplies plus a softmax — a range of linear algebra primitives already roughly baked into hardware. Going further means specializing not to the transformer but to a specific model: its layer counts, how data moves through and across layers, the exact shapes of matrices and vectors. He says a number of companies are pursuing that direction and calls it “very, very interesting.”

Co-design buys large multiples — and costs you portability
Vahdat lays out the trade-off with unusual clarity. A fully fungible system — one that runs on any hardware, any software, any network topology — can move to new capacity overnight and carries no lock-in. The cost: “Pros are you can run anywhere, anytime. You have no lock-in. Cons are you’re leaving significant, in all likelihood, significant amounts of performance on the table.”
He frames the payoff as a compounding one. “There might be 10%, 20%, 2x across each of these layers,” he said. “You start multiplying those optimization opportunities through, and all of a sudden you’re left with a big end-to-end opportunity in terms of whatever you want to say, intelligence per watt or goodput per watt.” That compounding extends all the way down to power delivery and power availability.
The relationship with Google DeepMind is where this becomes concrete. Vahdat describes hardware and model teams working in the same building, “same rooms many times, deep daily interaction,” and confirms he talks to DeepMind leaders Koray Kavukcuoglu or Demis Hassabis multiple times a week. DeepMind researchers can propose model optimizations and ask what hardware support would cost. Often the answer is that the original request is not feasible, but a modified version is — “we couldn’t quite do what you wanted, but we can do this other thing” — and the model architecture shifts to capture 90% of the benefit.
The asymmetry is real. Hardware is planned two to five years out; model architecture by default is not. The pipeline runs five or six stages deep — from chips in production back to chips in concept — and spans years. Sometimes Google delays a tape-out by one to two weeks because a model-side optimization justifies it, a capability that Vahdat says would be “somewhere between hard and impossible to do if we were working across company boundaries.”
Huang calls predicting five-year workloads impossible. Vahdat pushes back — the primitives have proven durable. The TPU instruction set has been extended since v1, but the fundamentals — specialized numerics for very large matrix multiply units, a sparse core handling vector operations and scatter-gather, remote load and store across the interconnect — have persisted across many generations of models and algorithms. He confirms Google is using Gemini to design hardware for future Geminis.
The agentic shift breaks the human rate limit
The most structurally significant change Vahdat identifies is the move from prompt-response to agentic workloads. In human-to-model interaction, the human is the rate limiter: you type a prompt, read the response, think, subscribe to the next request — seconds to tens of seconds per turn. “Now in Deep Horizon Agents, there’s no human in the loop,” he said. “So what went from seconds, maybe tens of seconds in terms of interaction time, is now going into perhaps milliseconds.”
The second change is where the work lands. Reasoning and parsing happen on CPUs, and those CPUs must gather state — from local DRAM, from another CPU’s DRAM, from SSD, or from HDD elsewhere. That orchestration load drives demand for accelerated compute and for traditional CPU, networking, and storage simultaneously. This creates a design problem with no clean answer: pack CPU racks next to TPU racks and you cannot fully specialize the building to either workload. Separate them into different buildings and you add networking complexity, cost, and latency — Vahdat estimates hundreds of microseconds or more with queuing between components.
Light switches and spare racks
Google began deploying wave division multiplexing inside its data centers roughly 15 to 16 years ago, and introduced optical circuit switching alongside it. The contrast with electrical packet switching is the point: a packet switch reads a header, looks up a destination, and forwards — billions of packets per second. An optical circuit switch never touches the bits electrically. It decides which output port to send light to, using MEMS mirrors controlled in 3D, so every input port on a 128- or 256-port box maps to an output port by physically reflecting light.
The TPU application is the more striking one. TPUs are connected in a torus topology, and Google keeps a spare rack available. When a TPU rack fails, the optical circuit switch redirects light to the replacement rack in milliseconds — no fiber moved, no human dispatched. Huang asks why not go fully free-space. Vahdat cites attenuation loss and dramatically reduced bandwidth, plus the difficulty of aiming everything in 3D across a very large building. But he notes that in orbital data centers — a moonshot Google is actively pursuing — free space “is now going to become reality,” with lasers pointing at receivers and calibrating in real time.
The one constraint nobody has solved
Asked for the single biggest constraint, Vahdat declines to name one — they are all hard and they shift continuously. Then he answers anyway. “There is no single biggest constraint that we face. They’re all constraints. They’re all super hard… But if I had to answer fundamentally, I would say that power is the single most fundamental constraint that we face.”
Everything else, he says, “seems like we know how to solve them and it’s a question of solving them over some period of time.” Power is different. The provisioning process is multi-year and utility-first. “You call very politely your favorite utility, wherever it is that your data center is,” he said. “And of course, you give them many, many years of notice. So in other words, if we’re talking about a gigawatt scale, it’s not something that you can say, hey, I need a gigawatt tomorrow.”
The mismatch case is instructive. If Google needs a gigawatt in 2028 and the utility can deliver 700 megawatts in 2028 but the full gigawatt in 2029, Google may self-generate the remaining 300 megawatts — solar, batteries as backup, or other sources — then provide power back to the grid during peak residential demand once the utility comes fully online, such as the hottest two weeks of the year.
The reliability math is stark. “If we need to have a gigawatt of power… with 99.99% plus reliability, probably means we have to build two gigawatts of power,” he said. That redundancy is why Google prefers working with utilities over vertical integration: statistical multiplexing across a much larger base means the grid, residences, and Google all win.
Vahdat offers a prediction with low confidence: abundant clean energy, potentially including nuclear, would solve many of the power constraints facing AI data centers, but when it arrives at scale remains unknown.

Old TPUs, new pods
Vahdat confirms a statement that drew more attention than he expected: Google’s seven- and eight-year-old TPUs are still at 100% utilization. Replacement is driven by depreciation and power efficiency, not idleness. The accounting lifetime is approximately six years, and once a generation is fully depreciated, newer generations’ power efficiency makes upgrading worthwhile.
The unit of replacement is the pod, not the chip. A TPU 8t pod might be 9,600 chips across roughly 152 racks. Google pulls the pod and replaces it with a newer one — and the new pod’s footprint may not match the old pod’s vacancy, so retrofitting is genuinely hard work that cannot be planned in advance because future generations’ dimensions are unknown.
On the training-versus-serving split, Huang’s intuition — newest clusters train frontier models, older ones get recycled for inference — is “very reasonable” but incomplete. Inference demand is too large to be served only by retired training clusters, and training clusters concentrate on one continent in a given year, leaving other continents short on serving capacity. So Google builds dedicated serving clusters too. Those are not necessarily cheaper per megawatt, because serving requires co-locating compute, networking, and storage, which forfeits the density and uniformity that training allows.
The internet argument for open standards
Vahdat’s case for open standards rests on the history of IP. Many protocols competed in the 1970s and early 1980s; IP won because it was an open standard and a narrow waist — anything could run above it in software and anything below it in hardware. He applies the same logic to Google’s stack: JAX is Google’s preferred framework and is used extensively internally, but customers who prefer PyTorch can run unmodified models through Torch TPU. The alternative — “if you want to run on TPUs, you got to use JAX” — is exactly the walled garden Google wants to avoid. He states plainly that the buildout is too big and too important to be any one vendor’s closed proprietary stack.
The unresolved tension running through the entire conversation is that every lever Vahdat pulls has a counter-lever. Specialization buys speed and power efficiency and costs flexibility. Co-design buys compounding end-to-end gains and costs portability. Separating CPUs, storage, and accelerators into different buildings preserves per-building optimization and adds networking cost, latency, and reliability risk. Utility partnership beats vertical integration on statistical multiplexing and depends on multi-year utility timelines Google does not control.
The one number worth tracking against all of this is the doubling cadence: Google has been told to roughly double effective serving capacity — measured in token generation, not raw FLOPS — every six months. Vahdat attributes as much or more of that to software — model and runtime optimizations landing “again and again and again” — as to hardware. If that cadence holds while power remains the binding constraint, the interesting question for the next several years is not whether Google can build the accelerators, but whether it can get the electrons. For the hyperscalers collectively spending hundreds of billions of dollars a year on this buildout, with revenue models that economists and analysts increasingly question, the arithmetic of goodput per watt and megawatts per dollar is where the bet gets won or lost. Vahdat’s message is that the physics are solvable. The power is the question.