TL;DR
Customer Exit: Microsoft has withdrawn from Nscale’s planned Loughton AI data center, leaving the project without its only publicly announced customer. Power Delay: Sufficient grid electricity is reportedly unavailable until the early to mid-2030s, years after the planned early-2027 deployment of AI processors. Project Continues: Nscale is exploring alternative power, while both companies say their wider partnership continues. Customer Concentration: Microsoft and AI developer Anthropic account for about 85% of Nscale’s reported future contract value as it prepares to go public.
Microsoft has withdrawn from Nscale’s planned AI data center in Loughton, Essex, UK, leaving the project without its only publicly announced customer while its electricity supply remains unresolved. The facility was intended to provide computing capacity for Microsoft’s Azure cloud services, with an initial processor deployment due in early 2027.
The Telegraph first reported the withdrawal on October 18. Microsoft subsequently confirmed that the decision concerns one site, telling ITPro on October 19: “This decision relates to a single site.” The company said it remains committed to its partnership with Nscale.
Nscale says it will continue pursuing Loughton and is exploring alternative power sources. Its spokesperson said the grid problem has no impact on its other Microsoft contracts.
A Computing Commitment Without Timely Power
Nscale, a British AI cloud infrastructure provider, was to develop, own and operate the center, with Microsoft as its main customer. Their September 2025 commitment envisaged 50 megawatts (MW) of AI capacity, expandable to 90MW, and an initial deployment of 23,040 Nvidia GB300 GPUs, or graphics processing units, in the first quarter of 2027.
Those GPUs would provide the processing hardware behind the planned Azure capacity. The megawatt figures describe the power-capacity scale of the facility, whose computing equipment needs an adequate electricity supply to operate.
The reported grid timetable extends years beyond that deployment target. UK Power Networks, the local electricity-distribution operator, reportedly told Nscale that sufficient power would be unavailable until the early to mid-2030s.
UK Power Networks said many data centers connecting to its local distribution network must wait for work on the wider national electricity-transmission network before they can operate. A local connection therefore depends on more than work at the data-center site itself.
Nscale has cleared the former scaffolding yard at Loughton and is investigating onsite generation as well as a faster grid connection. The timing and capacity of any alternative supply remain unclear.
In April 2026, Microsoft agreed to rent capacity at Nscale’s Narvik site in Norway, involving 30,000 Nvidia Vera Rubin chips. That agreement built on an earlier $6.2 billion Microsoft commitment at the same Norwegian site.
Large Contracts, Capacity Still to Build
Nscale filed for a proposed US public share offering on September 18.
A recent analysis of its filing puts Microsoft and AI developer Anthropic at about 85% of Nscale’s more than $103 billion in future contract value. Microsoft’s commitments totalled $43.8 billion through 2033, alongside a $44.6 billion supply agreement with Anthropic. The value of Microsoft’s ended Loughton agreement remains unclear.
Anthropic’s agreement depends on Nscale obtaining financing and lets the AI developer cancel if Nscale misses “stringent” milestones.
The scale of those agreements contrasts with a business still building much of its physical capacity. Nscale’s September prospectus listed five active data centers offering a combined 55MW, with another 12 in development. Large customer commitments underpin much of Nscale’s value while capital-intensive projects remain unfinished. Loughton was only a small part of Microsoft’s overall business with Nscale.
Nscale has also arranged financing for its wider expansion. A reported $3.36 billion pre-flotation funding agreement provides for $2.36 billion upfront and a further $1 billion from Nvidia by mid-November 2026. Nscale says the backing will help accelerate its global data-center construction. The financing notes would convert into shares at an initial public offering.