Microsoft Corp. (MSFT) undershot expectations on AI infrastructure spending by about $5 billion last quarter, and satellite imagery reviewed by research firm Aterio suggests construction setbacks at two outside data-center projects may account for part of the gap.
The Redmond, Washington-based company disclosed the shortfall on its quarterly earnings call last month and trimmed its annual capital expenditure forecast by the same $5 billion. Chief Financial Officer Amy Hood tied the miss to delays at third-party cloud providers without naming them. News of the cut weighed on shares of so-called neocloud operators, the young companies that have signed multibillion-dollar capacity deals with Microsoft.
Aterio’s analysis points to IREN Ltd. (IREN) and Nebius Group N.V. (NBIS) as possible contributors. IREN is building four data centers in Texas under a $9.7 billion agreement with Microsoft. A flyover on Oct. 21 found that one building, Horizon 4, still lacked backup generators and cooling equipment and could miss its scheduled delivery by the end of the year, according to the research firm, which compared optical and thermal images with earlier satellite passes from May, June and July. IREN previously said equipment shortages held up Horizon 1, which Microsoft accepted in August.
The second project sits in New Jersey, where data-center operator DataOne is developing capacity for Nebius under a separate $17.4 billion Microsoft agreement. Aterio data analyst Daud Shiraz said roughly 140 megawatts of that project’s planned capacity could slip into 2027 after difficulties securing permits for its original generators and further approval delays following a switch to fuel cells. Regulators fined DataOne $1 million in September for running generators without the required permits.
A Microsoft spokesperson said the company’s “approach to infrastructure is built on flexibility and optionality,” combining its own data centers with leased facilities and third-party providers. IREN and DataOne declined to comment, and Nebius did not respond to a request for comment.
The setbacks extend beyond those two sites. In October, Microsoft scrapped a planned 50-megawatt data center deal in the United Kingdom with neocloud Nscale, citing uncertainty over power supply, with grid access reportedly not expected until the 2030s. The site had been intended to house 23,000 of Nvidia Corp.’s (NVDA) GB300 chips.
The spending miss is not unique to Microsoft. Alphabet Inc. (GOOGL) also reported quarterly capital expenditure below analyst estimates, at $51.36 billion against $55.09 billion expected, while Microsoft spent $45.2 billion versus $50.7 billion forecast. The combined shortfalls have raised questions about whether hyperscalers can keep up the pace of AI infrastructure spending, a concern that ripples through the neocloud providers that depend on those contracts.
Research firm Currence estimates that 30% to 50% of planned data-center capacity originally slated to come online this year could be pushed into 2027 or later because of electricity shortages and other construction problems.
Political developments may add pressure. Technology analyst Dan Ives said Democratic gains in the midterm elections could slow the U.S. data-center buildout, estimating that 10% of planned construction would not proceed. Strategist Jim Bianco said Democrat Gina Hinojosa’s win in the Texas gubernatorial race could affect expansion in a state expected to host 25% of new U.S. data centers through 2030, flagging uncertainty over whether a construction moratorium imposed by Republican Gov. Greg Abbott will remain in place even though Republicans kept control of both legislative chambers.
For investors, the satellite evidence offers a concrete way to test whether the neocloud buildout is running on schedule. Companies such as IREN and Nebius have staked their valuations on delivering capacity on time, and any shift of megawatts into later years would hit revenue timelines and raise questions about the durability of the hyperscaler contracts underpinning them.