OpenAI faces second Effingham County delay on Project Camellia data center vote
OpenAI says it plans to continue working with Effingham County officials after commissioners delayed a decision on the company’s proposed data center for a second time.
In a statement to WJCL News, an OpenAI representative addressed the latest postponement, saying the county commission has the authority to delay the preliminary site plan review.
“The board of commissioners have the authority to defer any preliminary site plan review to a later date based on their bylaws. OpenAI will continue working closely with county staff and our commissioners to address any outstanding questions and keep the project on schedule.”
Why the vote was delayed
Effingham County commissioners voted Tuesday, Nov. 3, to postpone a decision on Project Camellia’s site plan until Nov. 17.
The proposed data center has raised concerns among commissioners, particularly about noise protections for nearby neighborhoods and whether the developer’s representative was prepared to answer questions about the project.
District 2 Commissioner Roger Burdette questioned the lack of clear commitments about a proposed 20-foot earthen berm that could help reduce noise and light impacts for nearby residents.
County planning staff had recommended approval of the site plan.
What’s next for the project?
Project Camellia is proposed for approximately 1,347 acres within the Savannah Gateway Industrial Hub, along Effingham Parkway and Gateway Parkway.
Plans call for six data center buildings, a warehouse and an operations building.
Commissioners are expected to revisit the site plan during their Nov. 17 meeting. They are also scheduled to discuss a possible data center moratorium and changes to the county’s rules for future data center developments.