Microsoft is tightening oversight of data centre projects involving specialist cloud providers as construction delays, rising costs, and regulatory issues affect infrastructure delivery.

According to Bloomberg, the company is reviewing projects involving Nebius, IREN, and Nscale. Citing people familiar with the matter, Bloomberg reported that Microsoft is stepping away from projects it considers too risky and internally discussing whether to sign additional agreements with neocloud providers.

Microsoft is also placing greater emphasis on developing its own data centres while continuing to use external providers for additional cloud and AI computing capacity.

In comments reported by Reuters, Microsoft said its infrastructure strategy combines company-owned data centres, leased facilities, and partnerships with external providers. The company has not announced plans to discontinue its use of third-party infrastructure.

Microsoft faces delays in third-party capacity deliveries

Microsoft disclosed delays in third-party infrastructure deliveries during its latest quarterly earnings announcement, before Bloomberg reported on the company’s review of neocloud projects.

During its fiscal first-quarter earnings call, Microsoft reported capital expenditure of $45.2 billion for the quarter ended September 30, 2026.

“Some third-party capacity deliveries we expected in Q1 were delayed,” CFO Amy Hood said during the earnings call, explaining the timing of the company’s infrastructure spending.

Approximately three-quarters of Microsoft’s capital expenditure went towards shorter-lived assets, primarily CPUs and GPUs. The remaining expenditure covered longer-lived infrastructure assets, including data centres.

Microsoft expects capital expenditure to exceed $50 billion in its fiscal second quarter. Hood said some third-party capacity deliveries had shifted into the second half of the fiscal year.

The company also expects spending to accelerate during that period, partly because of the rescheduled infrastructure deliveries. Microsoft projected capital expenditure of approximately $170 billion for calendar year 2026.

Microsoft has continued developing its own infrastructure alongside third-party projects. During the same earnings call, CEO Satya Nadella said the company added 24 data centres across five continents during the quarter.

Microsoft scales back Nscale expansion plans

Microsoft has decided not to exercise an option to expand its computing capacity agreement with UK-based Nscale at a separate site in Ward County, Texas, according to Reuters and the Financial Times.

The companies announced an expanded agreement in October 2025 covering approximately 200,000 Nvidia GB300 GPUs across facilities in Europe and the United States. Nscale’s original announcement included plans to deploy approximately 104,000 GPUs at a 240-megawatt (MW) facility in Ward County.

Nscale’s existing Texas deployment is located at a site leased from Ionic Digital. Microsoft also held an option to secure additional computing capacity at a separate Nscale-owned site nearby.

The proposed expansion involved approximately 500 MW of additional capacity. Microsoft decided not to proceed with the option amid difficulties securing the necessary electricity supply arrangements for the project.

Nscale corrected its October 2025 announcement on November 5, removing an earlier statement that Microsoft held a 700 MW expansion option. The correction did not remove the company’s separate claim that the existing Texas campus had the potential to scale to 700 MW.

A person familiar with the matter told Reuters that Microsoft made its decision several months before Nscale filed for its initial public offering in September 2026. The decision did not affect the existing Texas agreement or Nscale’s approximately $103 billion in disclosed contracted business across its operations.

Microsoft also withdrew from an agreement to become an anchor customer at Nscale’s proposed data centre in Loughton, Essex. The withdrawal followed delays to the site’s power connection, which pushed the expected electricity supply date into the 2030s.

IREN reports delays to Microsoft infrastructure deliveries

IREN, another provider working with Microsoft, has postponed deliveries of some AI infrastructure following changes to network designs requested by the software company.

The companies signed a five-year GPU cloud services agreement in November 2025, with a total contract value of approximately $9.7 billion. The agreement includes a 20% customer prepayment and provides Microsoft with access to Nvidia GB300 GPUs.

IREN also entered into an agreement with Dell Technologies to purchase approximately $5.8 billion worth of GPUs and associated equipment for the deployment. The infrastructure is being installed at IREN’s Childress campus in Texas, with deliveries scheduled in phases.

The project comprises four Horizon data centres designed to support a combined 200 MW of critical IT capacity. Each facility is designed to provide approximately 50 MW of capacity, with liquid cooling used to support high-density GPU deployments.

IREN said the first Horizon facility entered service for Microsoft during the quarter ended September 30, while the remaining three facilities had reached late-stage construction.

In its earnings announcement, IREN revised its target for reaching more than $4 billion in annualised run-rate revenue from the end of 2026 to January 2027, with a possible extension to the end of February.

“The more than $4 billion of contracted ARR is funded and now targeted for January,” IREN co-founder and co-CEO Daniel Roberts said in the announcement, attributing the revised schedule to a customer-requested design change and supplier timing issues.

The target covers IREN’s broader AI cloud operations rather than revenue from Microsoft alone. The figure is based on contracted GPU capacity and pricing and is not equivalent to revenue already recognised under accounting standards.

According to Reuters, IREN will not incur financial penalties for delays arising from Microsoft’s requested network design changes. The company has not announced any cancellation of its Microsoft agreement.

IREN also reported approximately $15 billion in remaining planned capital expenditure for fiscal year 2027. Of that amount, $9 billion is expected to be covered by cash, committed GPU financing, and customer prepayments.

The remaining $6 billion is expected to come from additional GPU financing, customer prepayments, data centre financing, and other corporate funding sources, subject to market conditions.

(Photo by Simon Ray)

See also: Microsoft licensing rules influence Azure cloud decisions, survey finds

Want to learn more about Cloud Computing from industry leaders? Check out Cyber Security & Cloud Expo taking place in Amsterdam, California, and London. The comprehensive event is part of TechEx and is co-located with other leading technology events, click here for more information.

Cloud Computing News is powered by TechForge Media. Explore other upcoming enterprise technology events and webinars here.