WASHINGTON (TNND) — Just two days after midterm voters rejected data centers in 40 of 41 local ballot measures and elected governors who pledged to pause new projects, OpenAI unveiled new policies aimed at rebuilding public trust as political pressure grows over the rapid expansion of AI infrastructure.

The company committed to paying the full cost of electricity and said it ended non-disclosure agreements with public officials, steps intended to increase transparency about construction and potential impacts. With Democrats now controlling Congress and key states, the debate is intensifying over whether voluntary measures will ease backlash or whether tighter regulations and moratoriums will slow the pace of new development.

Bridget Bean, former director of the Cybersecurity and Infrastructure Security Agency, told The National News Desk that data centers were not the main driver of election outcomes but became a significant factor in places where they were directly on the ballot.

“It certainly was an accelerant, not the engine,” Bean said. “Data centers didn’t decide the election; prices, the president, the war did.”

Bean said the ballot results were decisive: “Every single place where a data center was actually on the ballot, it lost.”

She pointed to Texas, where she said Gov. Greg Abbott “hit the pause button on new centers in September,” but still lost. Bean said she did not think voters believed the pause would be paired “with a real secure plan for the rate payers.”

Bean also highlighted a shift in Georgia, saying the state’s Utility Board flipped “the first time in 30 years,” calling it the organization that sets the terms power companies offer data centers.

In Florida, Bean said Byron Donalds “never backed down,” summarizing his stance as: “Build them, make them pay their own way, protect the water, and let the towns decide.” Bean said Donalds won and argued that data centers remain critical, saying, “Data centers are essential. Our economy, our homeland security, and our way of life depend on it.”

Looking ahead, Bean said she expects the pace of the AI buildout to slow in the near term.

“I think we’re going to see delays,” she said, adding that “the moratorium or pauses are going to have a very big impact.”

Bean pointed to an agreement involving Georgia Power that she said would allow the utility to reduce power to an OpenAI campus by 1,000 megawatts when the grid is stressed, “to make sure that there’s no power outages for the rest of the community.”

Bean framed the longer-term challenge as balancing voter concerns — including electricity costs — with global competition.

“The American people spoke very, very loudly,” she said. “What we cannot lose sight of is that we are in a race with China.”

“It is critically important that we remain the leader in the A.I. race because the world that accepts, you know, the A.I. model built in America is the one where individual liberties and freedoms prevail,” Bean said. “If China wins the race, we’re in a we are in a surveillance state, one that is beholden to the CCP.”

Bean said she believes it is possible to continue building while ensuring the public is informed and not forced to shoulder added costs.

“They are not incompatible,” she said. “We need to make sure we’re making good decisions, that we’re continuing to innovate, and that we’re continuing to win the race, but we don’t need to place the burden on people who aren’t on the voters.”