Oracle said Friday that its cloud infrastructure contract with OpenAI is fully funded, after a final capital raise earlier this month closed out the financing plan it laid out at its investor day. The shares climbed as much as 3.3% in after-hours trading.
In a post on X, the company said the financing it described at investor day, vendor financing included, is already in place, and that any further private talks with suppliers amount to optional extras rather than necessities. Oracle (NYSE:ORCL) also called itself the first hyperscaler to be fully funded for the current AI investment cycle.
The disclosure responds to persistent investor questions about how Oracle will pay for its data-center buildout and about how much of its future revenue rests on a single customer. Its five-year, roughly $300 billion computing agreement with OpenAI accounts for a large slice of the company’s remaining performance obligations.
At investor day, Oracle capped incremental capital-markets fundraising for the fiscal 2027 through fiscal 2030 investment cycle at $20 billion, split evenly between equity and gross debt and excluding refinancing. That sits on top of a $20 billion at-the-market equity program completed in the first quarter of fiscal 2027, alongside vendor financing, customer-supplied hardware and customer prepayments intended to trim upfront cash outflows.
Financing elementAmount / statusIncremental capital-markets raise, FY2027-FY2030$20 billion ($10 billion equity, $10 billion gross debt)At-the-market equity program, Q1 FY2027$20 billion, completedOther leversVendor financing, customer hardware, customer prepaymentsFree cash flow targetPositive in H2 FY2028; above $30 billion annually in FY2029
On the construction side, Oracle said its Abilene, Texas campus, where an OpenAI model was trained, is close to finished. Its next gigawatt-scale site in Shackelford County has all permits in hand, and delivery of Nvidia’s next-generation Vera Rubin racks to those halls is expected within weeks. Together with the original Stargate site in Abilene, Oracle and OpenAI plan 4.5 gigawatts of additional U.S. data-center capacity.
The update lands as analysts and investors press the broader AI industry on debt structures, off-balance-sheet arrangements and circular financing, in which chipmakers, cloud providers and model developers bankroll one another’s expansion. Oracle’s leverage and its concentration on OpenAI have been the focal points of that debate.
Oracle reaffirmed its guidance, including a return to positive free cash flow in the second half of fiscal 2028 and more than $30 billion in annual free cash flow in fiscal 2029. Management has framed that milestone as the point at which the company can fund growth internally instead of returning to capital markets.