The Huntingwood site is in an industrial precinct about 10 kilometres west of Parramatta (Image: Google)

Microsoft has won New South Wales government approval for an A$1.3 billion ($901.9 million) data centre in western Sydney, three days after Goodman Group withdrew plans for a hyperscale facility on the city’s north shore in the face of neighbourhood opposition.

The NSW Department of Planning, Housing and Infrastructure on 1 October granted consent for the Honeman Close Data Centre in Huntingwood, an industrial precinct 3.5 kilometres southwest of the Blacktown town centre and 10 kilometres west of Parramatta. The facility will house 40 data halls across five floors with 96 megawatts of IT load, according to the department’s assessment report.

The approval adds fresh insight on the challenges of site selection facing data centre developers in Sydney. Microsoft’s application drew a single public submission, an objection over emissions, even though the nearest homes are about 90 metres from the site. Goodman’s Project Mars, planned 20 metres from the nearest house, drew 374 public submissions, only nine of them supportive.

The department cited capital investment of A$1.26 billion, 250 construction jobs and 74 operational roles among its reasons for approval. Construction is expected to take about 24 months, adding to an Australian build-out for which Microsoft in October 2023 committed A$5 billion over two years. The project carries a capital cost of about A$13.2 million per MW, compared with A$9.9 million for the 81MW Project Mars, according to Mingtiandi calculations.

Federal Sign-Off Pending

The state consent is not the last hurdle facing the tech giant. Microsoft still needs a separate federal environmental approval because the building would clear 0.33 hectares of a conservation area containing critically endangered woodland and potential habitat for endangered wildlife, according to the assessment report. The application is being assessed under the Environment Protection and Biodiversity Conservation Act, and work cannot proceed until it is granted.

Brad Smith of Microsoft

Microsoft president and vice chair Brad Smith (Image: Microsoft)

Before the data centre can start operating, Microsoft must also show that all of its electricity demand is matched by additional, firmed renewable supply, secured through power purchase agreements for NSW-based generation, according to the development consent. The department estimated the facility would generate 1,326 kilotonnes of carbon dioxide equivalent in its first year, mostly from electricity use.

The consent caps total power consumption at 140MW. Back-up power will come from 46 diesel generators, with up to 1.5 million litres of diesel stored on site and 158,763 kilograms of lithium-ion batteries bridging any outage until the generators take over. Cooling relies on 36 rooftop evaporative cooling towers, and the facility is expected to use about 3.9 megalitres of water a day.

Three-Year Wait

The application was lodged in 2023 by engineering consultancy Lehr Consultants International without publicly identifying the end user, Data Center Dynamics reported at the time.

While Microsoft received its approval this month, public exhibition of the project proposal, and the window for public commentary, had closed on 1 February 2024, more than two and a half years before Goodman withdrew its A$798 million Project Mars plan last week in the face of local opposition. Goodman’s Project Apollo was approved about 16 months after its exhibition period ended.

Much of the interval between the close of the exhibition period and approval of Microsoft’s project went into negotiations with Blacktown City Council, which raised concerns about the building’s bulk, landscaping and drainage, before withdrawing its objection after several meetings. Microsoft’s data centre entity signed a planning agreement with the council in September 2025.

Huntingwood sits beside the Eastern Creek data centre cluster, where Starwood, Doma and Telstra InfraCo are developing a 62MW facility in neighbouring Minchinbury on a development-approved site. Goodman earlier this year filed for an environmental assessment for a plan to invest A$5 billion on a 500MW data centre in Eastern Creek, dubbed Project Atlas.

Neighbours Matter

In addition to rising suspicion among the public regarding data centres, Goodman’s Project Mars, located in Lane Cove West, sat 160 metres from a primary school, and Sydney Water had asked for the assessment to be deferred pending further study of the local water supply, Mingtiandi reported last week.

Guy Smith, Goodman’s head of planning, told the department on 28 September that the policy environment for large data centres had “evolved significantly” since the company began planning the project in March 2025.

The rules are still shifting. Victoria’s government has proposed a 150-metre buffer between data centres and homes, a distance that would take in the houses nearest the Huntingwood site. National Cabinet agreed in August to develop mandatory national standards for large data centres, with the Commonwealth committing to legislate in early 2027, though Prime Minister Anthony Albanese has said the rules would not apply to projects already approved.

Stockland Goes Vertical

On the same day that Microsoft won its approval, the New South Wales government also granted consent to Stockland’s development application for its Road 1 Data Centre, a A$630.4 million facility at 1-5 Khartoum Road in Sydney’s Macquarie Park.

Stockland’s project on the site of a former Johnson & Johnson campus is designed for 34.3MW of IT load and 49MW of total power capacity, according to the department’s assessment report. The facility will adjoin a 76.4MW Stockland data centre approved in March and sits in the same Macquarie Park precinct as Goodman’s Project Apollo.

The application drew five public submissions, three of them objections, and the City of Ryde council did not object to the project.

Because Stockland also plans build-to-rent apartments on former Johnson & Johnson site, the department required air quality modelling for future homes up to 39 floors above the data centre. Stockland responded by specifying higher-performance generators fitted with catalytic reduction systems that cut nitrogen oxide emissions by 85 percent. Its consent carries the same requirement as Microsoft’s to match all operating electricity demand with firmed, NSW-based renewable supply.