Former Cross River Rail Delivery Authority industrial relations consultant Rob McPherson has told the CFMEU Inquiry he was pushed out of his role following union complaints to Deputy Premier Jackie Trad’s office.

In November 2018, CRRDA chief executive Graeme Newton called Mr McPherson into his office.

“I’ve got to go and see Jackie Trad about you,” Mr McPherson said Mr Newton told him.

“Sorry, mate, but I have to let you go.”

Earlier, Cross River Rail project manager Jamey Purvis made the explosive revelation at the inquiry today saying despite the worksite being “chaotic and like a war zone”, he was told to “not to contact police”.

The inquiry has concluded for the week.

Hearings return 10am October 27 with a further ten witnesses scheduled to give evidence on Cross River Rail matters.

FOLLOW OUR BLOG BELOW

4.06PM: The final witness today is Cross River Rail shared services administrator Jessica Allam.

Ms Allam was involved in development training and redundancy and redeployment processes.

She also checked and conducted right-of-entry requests.

Ms Allam said the CFMEU often issued several right of entry notices at a time.

“Sometimes they do give right of entry almost daily, or sometimes twice or three times a week. But sometimes nothing at all,” she said.

Ms Allam said when a wave of CFMEU notices came in, it exhausted IR resources.

She gave an example of CFMEU delegates getting close to her face.

“But like I, I just keep saying to myself, you know, you don’t respond to those aggression that they’re trying to show,” she said.

“So I do diffuse the situation sometimes by making some lighter jokes.”

Ms Allam said in April 2024, a supervisors reported to her that employees at the Roma Street Station site had been pressured by the CFMEU to vote in a ballot for protected action.

“They felt like they’ve been targeted by the CFMEU HSR on site to vote, and these two employees would like to make a formal complaint against it,” she said.

The CFMEU undertook extensive strike action at the Roma St site in 2024.

Strikes and protests began after Enterprise Bargaining Agreement (EBA) negotiations collapsed between lead contractor CPB and the CFMEU.

Cross River Rail Delivery Authority CEO Graeme Newton earlier testified that the CFMEU’s targeted disruptions caused the project to lose two full years of progress.

Ms Allam said workforce morale dropped significantly during the strike period, which lasted 148 days before a deal was brokered in December 2024.

Ms Allam has been excused. She was not cross-examined.

CPB abandoned its Northern Portal leadership team

3.49PM: Witness Peter Bennett said he and his supervisor colleagues were then instructed to work from the CRR Milton office for a couple of weeks.

He said workers tried to ask CPB what the plan was to help people return to site but received “nothing”.

“No contact, no IR managers, HR managers, shared services, contacted us at all to say “look, are you OK? We acknowledge what’s happened,” he said.

“There’s multiple people that had their kids’ names mentioned, kids’ schools mentioned, like how they got this information, is very serious and should be taken seriously.

“That’s why I couldn’t understand why there was no support from our company to protect employees from this type of harassment.”

Mr Bennett described the July 2023 week as “terrifying”.

“If normal people that don’t know what that sort of arena is like are crying, and besides themselves, and that physical fear in our staff’s eyes, that’s yeah, that’s enough for me to say this is a this is a serious criminal offence,” he said.

“We need help.

“We’re in fear.”

Mr Bennett said he, Shane Rasmussen and Peter Cullen all “begged” CPB human resources for help.

“We begged in HR. We wrote witness statements of situations. We asked what our position was,” he said.

“Because there was no contact… (Shane Rasmussen) went on medical leave.

“I went to see WorkCover and a psychiatrist to discuss, I suppose, the feelings of abandonment and protection and threats and which I took quite seriously.”

Mr Bennett said he was then moved to a different role at Roma Street.

He said he believed the CFMEU requested he and Mr Rasmussen and Mr Cullen be removed from the Northern Portal site as part of the safety reset agreement between CPB and unions.

“I believe that we were number 13 or number 14 on that list to be removed from site,” he said.

“This was quite a real situation for us, and I was, you know, I’ve worked for CPB on other projects, and I’ve worked for some quite large tier one infrastructure companies, and this is the first time I’ve ever seen something that was so inept of responsibility, and I still can’t believe it.

“I still can’t believe we’re sitting here talking about it because it’s you know we’ve got codes of conduct, we’ve got responsibilities that we have under the Act that we’re supposed to adhere to, and to fundamentally like not even acknowledge that is well, it’s disgusting for the people.

“I’ll use the three key words that CPB live by: integrity, honesty, and …accountability.

“All those three were ignored by the senior leaders to us – and that’s their motto.”

Mr Bennett has been excused. He was not cross-examined.

Sawn-off shotgun, machete, bats, knuckledusters

3.35PM: Cross River Rail senior supervisor Peter Bennett has taken the stand.

Several parts of his witness statement – nearly 34 paragraphs – have been redacted.

Mr Bennett specialises in electrical work.

He worked at the Northern Portal site overseeing mechanical and electrical installation.

Mr Bennett also conducted site walk troughs with unions.

He said the period around July 2023 was difficult as the UGL enterprise agreement had expired and lots of union representatives were on site to discuss upcoming negotiations.

“Those negotiations went from bad to worse really quick,” he said.

“We had two weeks or 14-hour days with the unions, going through everything and anything.”

Mr Bennett said the workforce “sat on the grass”.

After the worker fell from scaffolding at Boggo Road on July 25, 2023, Mr Bennett said tensions escalated.

On Thursday, two days after the incident, he said rocks were thrown at the crib rooms.

“I grabbed my car and I brought my car into the back gate, and we heard, you know, well, I witnessed some union members with CFMEU screaming out that “you got blood on your hands, we know where you live, we’re going to follow you home”.

Mr Bennett said there was a “heightened sense of fear”.

“One of our female engineers started crying,” he said.

“There was young, culturally diverse engineers that didn’t know what to expect.

“Shane and I consoled them, letting them know to just go home early or people to their cars, made sure that they got home early.”

On Friday, Mr Bennett was at the worksite when CFMEU members arrived armed with weapons.

“So more people have been brought in, and it’s amplified,” he said.

“I parked the car…there is a little car park up near that Victoria Park area where we were.

“(Jayce Emmerton) came running over to the car, he said “Pete, there’s some really bad people here.”

“And we looked up towards the to the front of Victoria Road, and there’s six men standing there, and they’re big men.

“Jayce proceeded to tell me that those guys have got weapons and it’s serious. Don’t go in.”

Mr Bennett said the men fit a “stereotypical bikie look”.

“They’re on steroids. They’re big,” he said.

“We heard through conversation some five to six weeks later that members of the Comanchero had been flown up from Victoria to support the situation, and members of other outlaw motorcycle gang in the Gold Coast had come up to help as well.”

Mr Bennett said he then called Mr Emmerton.

“And Jayce confirms that he’d seen a sawn-off shotgun, seen a machete, seen you know two baseball bats, he’d seen guys with knuckle dusters,” he said.

“He said they’re known to him to be part of a bikie group.

“And I said to Jamie, “Let’s call the police.”

“He said, “No, just wait” and he made he made a phone call to Milton (office), and then he came back and he said, “Everyone’s to go home”.

Mr Bennett then helped his colleagues escort engineers to their cars and shut down the site, including turning off generators and fridges.

‘Sorry, mate, but I have to let you go’

3.05PM: Mr McPherson said he was effectively pushed out of his role and replaced by Paul Inches, despite Mr Inches not appearing qualified for the job.

“To my understanding, is that the unions made complaint to the deputy premier’s office, the CEO of the Delivery Authority, Graham Newton, told me that he had been requested to attend a meeting with the Deputy Premier Jackie Trad about these issues, and in due course, as these meetings later in the year started to commence, I was not required to attend them,” he said.

Mr Inches was then engaged as the liaison between the CRRDA and unions.

“When I inquired about Mr Inches and his employment, It was put to me that he was just going to be doing training, and you know I took issue with that immediately because I knew of Paul and his background and career,” he said.

“I had at that time a copy of Mr Inches’ CV and… he had a long career at that time in and around the union movement.

“He also had a career, I believe, in and around government and being policy adviser to government ministers here in the state of Queensland.

“None of that’s a criticism. He’s entitled to his career, but none of that CV, on its face of it, showed any history or background in construction.”

Mr McPherson said unions refused to speak with him.

He received a call from AMWU secretary Rowan Webb who said: “Mate, so you know, we’ve all been talking. We know you’re calling us all. No one’s calling you back. We don’t know how you got the job. We’re pissed off. You got the job, and we want you out of the job.”

In October 2018, Mr McPherson’s boss Matthew Martyn-Jones told him:

“Look, don’t ask how this has arisen, but we’ve met with Paul Inches, we’re going to be using him as consultant to work with the unions on training. We need you to work with this, make life easier.”

Mr McPherson said Mr Martyn-Jones said the direction came “via the unions, via the Deputy Premier’s office.””

At this stage of the project the CFMEU and ETU were demanding the CRRDA adopt an enterprise agreement directly with the unions.

Mr McPherson opposed this.

Weeks later, in November 2018, CRRDA chief executive Graeme Newton called Mr McPherson into his office.

“And he said, “Mate, I’ve got a problem. It’s with you and your employment. I’ve got to go and see Jackie Trad about you,” Mr McPherson said.

“Sorry, mate, but I have to let you go.”

Mr McPherson said he warned Mr Newton that the CRRDA needed to maintain independence through its external advisers.

“If the unions, because they don’t like the director of industrial relations, can reach through the deputy premier’s office, as it was put to me, and request my removal or create an issue with my employment, then that’s, to my mind, that’s a governance problem,” he said.

“Because the right response to that surely is to say it’s not a matter at all for the unions who’s employed by the delivery authority to fulfil the role of the director of workplace relations.”

Mr Newton later told Mr McPherson that he “survived” the Trad meeting.

But he was no longer to attend meetings with the unions, which had refused to engage with the CRRDA if Mr McPherson was present.

“I can recall saying to both Graham and Matt, “Look, guys, this is as common as muck that the unions will say we’re not coming if that bloke’s there, right?

“And my guidance to them was the golden rule: it’s your project, right? They will come because, first of all, the CFMEU need to be there to be engaged and involved.

“They don’t have rules of coverage, and secondly, they won’t want meetings to occur with the AWU that they’re not at.

“So don’t blink, keep going, and they’ll come to heel.”

Mr McPherson did not attend any CFMEU meetings.

Mr McPherson has been excused. He was not cross-examined.

‘Because we’re in the family of government’

2.23PM: On July 18, 2018, an unknown woman attended a CCRDA meeting and provided Mr McPherson and chief executive Graeme Newton with a copy of the CFMEU-approved Best Practice Principles document.

“That was the first time we’d actually seen what was pretty close to the final version, and I distinctly recall the meeting because the comment that was made to us was that “because we’re in the family of government, I can tell you that this document’s hot off the desk of the CFMEU”” Mr McPherson said.

“So I was quite struck by that at the time.

“It’s a sort of comment that stays with me.. it reflected the extent to which the CFMEU were able to, or on the face of that comment, influencing the government around its procurement policies.”

Mr McPherson said he could not remember who the woman was.

While he initially thought the proposed Best Practice Principles could be managed, he later realised the CRRDA was expected to implement wage conditions on contractors which he deemed inappropriate.

“At that stage, the project was a five and a half billion dollar project,” he said.

“It’s not appropriate, in my view, for a government or a government entity to get involved in giving that level of granular direction and guidance to commercial entities who contractually are taking that risk.

“That’s not in the interest of the Queensland taxpayer.”

In February 2019, the CRRDA was issued a letter from then-deputy premier Jackie Trad outlining the government’s expectation that the Best Practice Principles be adopted.

Mr McPherson said at this point, it was clear CRRDA was being asked to implement the CFMEU’s Queens’ Wharf agreement.

“There’s two mentions of Queen’s Wharf in this letter,” he said.

“It’s an entirely different thing to have a set of best practice principles that articulate procurement principles about how the government expected the delivery authority to go about the procurement of the project—that’s appropriate, not unreasonable.

“But this letter goes further than that, in my view.

“In my view, this letter is capable of creating the inference, and I think it did in fact create the inference within the delivery authority that what was expected was Queen’s Wharf wages and conditions.

“I consider the letter unambiguous in that regard.

“The letter doesn’t say these are the best practice principles. Please make sure you comply with the best practice principles.

“It goes further than that.”

CRRDA worker takes the stand

2.07PM: Cross River Rail Delivery Authority (CRRDA) industrial relations consultant Rob McPherson has taken the stand.

Mr McPherson worked under CCRDA chief executive Graeme Newton.

He also assessed tender bids for the project during its procurement phase.

“All of the bidders had to put in a bunch of materials around their approach to industrial relations, what industrial instrument strategy they would have, what you know, what their approach to attracting and retaining labor would be,” he said.

“What the IR risks were that they foresaw, the mitigations of those risks, who they would use for external legal support, a range of industrial relations, matters like that were part of what they had to provide to the delivery authority.”

Mr McPherson said the controversial Best Practice Industry Conditions (BPICs) policy, formerly known as Best Practice Principles, were used as an assessment measurement for procurement during the second tranche of bidding.

Mr McPherson said the AWU had the “lion’s share” of coverage for CRR works.

“Obviously, the unions’ rules and the coverage rules of the unions determines what they can appropriately be able to bargain for and to have coverage of on a project,” he said.

“For this project, it was predominantly, not exclusively, a tunnelling project, so the lion’s share of coverage resided with the AWU.

“And certainly commercially and from a construction scope perspective, they had the biggest part of coverage of the project.”

Mr McPherson said the CFMEU, in comparison, did not have coverage rights.

He said the CFMEU used the government to “shoehorn” them into negotiations.

“I can recall conversations within the delivery authority, including with the roles that I reported to, about why the CFMEU, from very early on in my tenure were agitating through government into the delivery authority for engagement quite so aggressively,” he said.

“There were queries from within the project and the Delivery Authority about why the CFMEU was being so animated so early in the process.

“And the answer to that question is because they didn’t have coverage, and because they didn’t have coverage, my view and guidance to the delivery authority was that they would be seeking the assistance of the government to shoehorn them into the into the project, into the negotiations.”

Upper management’s bombshell direction

1.06PM: Cross River Rail project manager Jamey Purvis has taken the stand.

He has appeared via video link to give evidence due to a disability which prevents him from attending the inquiry in person.

Mr Purvis went to the northern portal site after hearing a man had fallen from scaffolding on July 25, 2023.

The following day, he went back to site and saw the gates were locked.

Mr Purvis said more than 100 tradies were blocked from working that day, with nightshift workers also turned away.

“I saw a police vehicle arrive to site, make a U-turn without stopping, and leave,” he said.

“The officers did not get out.

“I do not know why the vehicle attended or why it left.”

Mr Purvis said tensions escalated on Thursday, with rocks thrown at cars.

On Friday, Mr Purvis was called back to the site and told that CFMEU “mercenaries” had arrived from Victoria.

“They were manic… some wearing balaclavas,” he said.

“Some of those men were armed.

“I was at the front gate, there were cars blocking the front gate.

“Our staff were inside the facility with the gates locked.”

Mr Purvis said supervisors had “pretty much confirmed with me the other comments people have made over the previous few days about weapons”.

“Being knives, chains, and potentially a gun that was spotted around the northern portal,” he said.

“I took that in a pretty bad light.

“I was told people were hiding in the bushes.

“I believe it was a tactic to scare the work crew.”

Mr Purvis tried to report this to his superiors but all upper management were in the safety reset meeting with CPB and the unions, including the CFMEU, AWU and ETU.

“So the same day that there were allegedly at least one firearm at the northern portal was the same day of the safety reset meeting,” he said.

Mr Purvis drove to the office and waited five hours for the meeting to end so he could report the gun on site.

“I considered it to be pretty unstable in that situation, you know, confirmation that there was potentially real weapons on site,” he said.

The Cross River Rail site was then evacuated.

In an astounding revelation, Mr Purvis said upper management told him not to contact police.

“We didn’t call the police because we were actually told not to call the police a couple of days prior to that,” he said.

Mr Purvis said he believed this direction came from Human Resources Director Chris Butler.

“Thirty years in the government. I’ve never seen something like this occur in my career,” he said.

“You know, we’ve always had you know some arguments with unions, but never this escalation, this chaos; it almost felt like being at war at times.”

Mr Purvis has been excused.

He was not cross-examined.

The Inquiry will return at 1:45pm.

Union officials loitered, then threw rocks

12.37PM: Mr Rasmussen said on Friday July 28, 2023, two CFMEU officials worked out how workers were entering the northern portal and started loitering near the gate.

They then realised where Mr Rasmussen had parked his bike and began throwing rocks.

“So as soon as we heard loud crashes in and around the building, side walls and on roofs,” he said.

“It was not just myself, my vehicle, which is I ride a motorcycle, there was cars that were parked in around that area as well, and we relocated them at this point because of the debris being thrown in and around the office area.”

Mr Rasmussen said CFMEU members again threatened that he was not safe and they were going to “come and get me”.

He wrote to CPB management about safety issues involving the CFMEU at the site.

“I did want a response from senior management, I was unsure at that point in time to what information they actually knew of what happened through those weeks and or the days in that week, and I wanted them to be aware of the situation that we had been put under, which was at no fault of our own,” he said.

“If we went back to the site, I wanted to know what sort of precautions or actions they would take place in order to make our work environment safe.

“I had huge doubts that the company had commenced any sort of action in any sort of form to ensure the safety of not just myself but the other workers working at the northern portal.”

Mr Rasmussen did not return to the northern portal site after July 28.

He worked from home up until January 2025 when his contract with the CRR ended.

He said the experienced deeply affected his mental health.

It led him to seek psychiatric help over several months.

“Driving into work and home every day was a vigilant exercise in trying to assess who was in and around me, and if there was anyone that I believe was of a suspicious nature,” he said.

“I was concerned that I was being followed, for a start… I didn’t want that vehicle or person finding out ultimately where I lived.

“I didn’t want them to be following me all the way home.”

Mr Rasmussen said he sent return to work plans to CPB but received no feedback or direction from the contractor.

“I believe that CPB were playing a strategic game and trying not to get involved,” he said.

“I was advised that my services were no longer needed.”

Mr Rasmussen has been excused.

He was not cross-examined.

Baseball bats, balaclavas, Boggo Road

12.21PM: The Commission of Inquiry has called Shane Rasmussen to the stand.

He is appearing via video link.

Twenty-two paragraphs of his witness statement have been redacted.

Mr Rasmussen was the electrical superintendent for the northern portal site on the Cross River Rail project.

On July 26, 2023 – the day after the serious safety incident where a worker fell 15m from scaffolding at Boggo Road – CFMEU officials went to the northern portal site and instructed workers to march.

Mr Rasmussen said no work was completed on July 26.

That evening, Mr Rasmussen said nine CFMEU officials and one ETU official rushed the northern portal site during night works and “stormed” through the gates.

Mr Rasmussen said the officials accused him of forcing workers to work that night.

He said he was verbally threatened by CFMEU official Matthew Vonhoff.

“They said they know how I get to and from work, they know that I ride a bike and what bike I ride and that they will come and get me,” he said.

Mr Rasmussen said this “shook” him.

“I was concerned and unsure of my wellbeing that evening,” he said.

Workers were directed to go home for the night.

The following day, on July 27, the CFMEU was again outside the northern portal site.

Mr Rasmussen said about 15 to 20 members were there telling people to leave the site and that no work would happen that day.

“About 7:30pm they got a chain they had themselves and locked the front gate,” he said.

On Friday, July 28, Mr Rasmussen returned to work at 4:30am to enter through a backgate.

He said tensions had escalated by this point, and several cars were now blocking the front gate.

Mr Rasmussen said he was preparing to let workers in through the back entrance and called Jayce Emmerton to check on the workers’ location.

Mr Emmerton told Mr Rasmussen that the situation had escalated significantly.

“He was instructed by CFMEU as well to leave the northern portal and if he did not, they would take whatever action was necessary,” Mr Rasmussen said,

“He advised me that he had seen they had baseball bats, knives and were armed.”

Mr Rasmussen said he saws some CFMEU officials wearing balaclavas carrying a baseball bats.

The Cross River Rail site as then evacuated.

"Peeping Pete": Witness recalls CFMEU's bizarre accusations‘Peter, Peter, pumpkin eater’

11.22AM: On April 15, 2020, three CFMEU officials—Luke Gibson, Andrew Blakley and Matthew Parfitt—attended the Boggo Road worksite.

Their presence delayed a concrete pour and tunnelling works.

It led to court action through the Australian Building and Construction Commissioner (ABCC).

Mr Blakely and Mr Gibson were each fined $12,600.

The CFMEU was fined $126,000.

During the 2020 incident, Mr Gibson called Mr Cullen, “Peter, Peter pumpkin eater.”

Mr Cullen said at first he didn’t realise that the phrase referenced a sexual act.

“Look, I didn’t think much of that other than it was extremely childish, and it was something that he could sort of conjure up at the time,” he said.

“My supervisor Matt Gallon, who he understood that terminology, and I didn’t, but he did.”

Mr Cullen said the phrases “Peter, Peter, pumpkin eater” and “Peeping Pete” were regularly thrown around the worksite, including by his own colleagues.

“I also bore the brunt of many jokes and smart alec comments relating to my “hanging around toilets”, which were likely intended to be funny, but began to perpetuate a legacy about me that was insulting and defamatory,” he said.

Mr Cullen said the CFMEU weaponised these phrases, accusing him of following organisers into toilets to stand over and intimidate them.

He said CPB contacted him after the CFMEU issued an official statement in July 2020, stating he was following members into toilets.

Mr Cullen said the impacts on his reputation seriously affected him, to the point where he was concerned about taking his daughter to the toilet in public.

“Female workers, would find me even less approachable, due to their concerns I may act inappropriately towards them,” he said.

“My concerns over the comments, coupled with the fact friends and family had seen the media statement or subsequent media articles and begun asking questions about its origin, became a catalyst for tension within my immediate family.

“My home life began to deteriorate as a consequence of all the attention and uncertainty

CPB management approached me and asked if I wanted to commence a defamation lawsuit.”

Mr Cullen agreed and launched a lawsuit against the CFMEU and former leader Jade Ingham in February 2021.

“I’ve got a lot of friends and relatives on Facebook, and once it like went on to Facebook, then that got passed around, so regardless whether it’s completely untrue, there was no sort of condemnation as but as such, so and because I couldn’t respond to it, because I could be seen to be escalating it… I felt perilous to defend myself,” he said.

“Even today, people will still remember that.”

Mr Cullen said CPB attempted to elicit an apology from the CFMEU but the union refused.

“We didn’t resolve it. They still stood by what they said,” he said.

“I think there was some concession in regards to not the removal of the post, but there was no retraction, no apology.”

Mr Cullen said his mental health was impacted by the CFMEU campaign against him.

He went on sick leave for several months and put in a workcover claim.

“I went to bed, it was on my mind, I woke up, it was on my mind,” he said.

Because of this sick leave, Mr Cullen was not on site when a worker fell from scaffolding on July 23, 2023.

Mr Cullen said he remains psychologically impacted today.

“That particular element of the CFMEU… has distorted my view and opinion of the CFMEU,” he said.

“Every time I see a CFMEU flag, sticker, t-shirt., it opens issues.

“It’s painful as a memory… I didn’t get validation or exoneration.”

Mr Cullen said today’s hearing was an opportunity for him to get validation and tell his truth.

Commissioner Stuart Wood asked if Mr Cullen wanted an apology from CPB bosses Vince Sanfilippo and Don Johnson.

“I would, it’s a little bit late, but I still would,” Mr Cullen said.

He has now been excused from the stand.

Commissioner Wood said while Mr Sanfilippo and Mr Johnson had also already been excused, they could be recalled to answer questions about why they failed to protect Mr Cullen.

Mr Cullen was briefly cross-examined by barrister acting for the CFMEU Administration Chris O’Grady.

Mr O’Grady asked Mr Cullen to confirm that he knew the CFMEU was no longer associated with Jade Ingham and that all defamation proceedings had been discontinued “on the basis that there would be no order as to costs”.

Mr Cullen agreed.

“I believe so, yes,” he said.

Mr Cullen has been excused from the stand.

‘It boggled me as to who called them’

10.45AM: Mr Cullen said the CFMEU arrived on site on the very first day of construction in August 2019, claiming they had been called about a safety complaint.

Mr Cullen could not explain how a safety call was made on the first day of work.

“It boggled me as to who called them,” he said.

“There’s no possible way.

“All we were doing was setting up a marquee…there was no high risk activity, no machinery, no tools or equipment – just using pegs , hammers, measuring tapes.

“But they turned up with a 117, with safety suspected contraventions.”

Mr Cullen said the CFMEU would often issue vague safety claims including poor amenities or access egress issues.

He said he would ask for clarity but the CFMEU would refuse, saying details would then identify workers who were reporting the safety issues with the union.

“So in fear of them getting pinpointed for raising a safety issue, they wouldn’t tell us specifically where the safety issue was,” Mr Cullen said.

Mr Cullen said most Workplace Health and Safety inspectors followed the book, but some seemed to favour the CFMEU and its version of events.

He specifically singled out inspectors Chris O’Donnell, John Azcune, Travis Dungy for lacking independence.

Horrific Cross River Rail safety incident

10.30AM: The CFMEU Commission of Inquiry will today explore the horrific Cross River Rail safety incident in 2023 when a worker fell 15 metres from scaffolding.

Nation “Nash” Kouka” 54, plunged from scaffolding at the Boggo Rd station construction site about 1.15pm on July 25, 2023.

Several witnesses will be called to give evidence on the incident, which prompted a safety reset across all Cross River Rail sites.

This included contractor CPB agreeing to hire 14 CFMEU-appointed Health and Safety Representatives (HSRs).

Peter Cullen has taken the stand.

He was the very first safety adviser appointed to the CRR Boggo Road site.

CFMEU members block access to worksite

Several paragraphs of his written statement – under a section titled “ETU July 2023 incident” — have been redacted ahead of his evidence today.

Counsel assisting Eddy Gisonda said the paragraphs had been redacted to avoid unnecessary cross-examination from the ETU.

It comes after the hearing on Wednesday heard former deputy premier Jackie Trad tried to broker a union deal giving the CFMEU access to the $9bn Cross River Rail project.