The power crunch on Sydney data centre developers will leave critical projects in limbo for years and has crippled even the most rigorous projects, putting a $50bn-plus pipeline at risk.
A mismatch between the industry’s huge power requirements and restricted grid capacity ahead of upgrades in the next decade is recasting the cityscape and sparing no-one.
Data centres were told in August that Sydney was sold out of electricity capacity, and the industry must foot the bill for expensive network expansions after developers flooded network operator Transgrid with requests.
The effective rationing of power supplies is causing delays for big data centre developers bringing their operations online, while more speculative players may shelve projects entirely amid intense competition for electricity.
Transgrid told The Australian it had recently signed connection agreements with data centres representing 1.5 gigawatts of new demand in western Sydney, effectively doubling the load in that area.
“We continue to work with data centre proponents in response to unprecedented demand for electricity in western Sydney, where demand to connect has significantly increased,” a Transgrid spokesman said.

The transmission company may pursue a plan to unlock up to 2GW of extra capacity in western Sydney along with supplies in the less populated Riverina and Hunter regions, where existing power capacity is available.
Developers also face the thorny issue of complying with Anthony Albanese’s rule that data centres find new renewable energy supplies to power their factories, aimed at avoiding any further strain on Australia’s fragile power grid.
This mandate will add to the timeline for delivering new data centres, according to industry group Data Centres Australia. “The challenge remains in the time gap between building a data centre, which takes 18 months to two years, and a renewable energy project that can take from four to seven years,” group chief executive Belinda Dennett said.
“Data centre projects need to have a confirmed commitment to energisation in order to execute customer contracts, secure capital and commence the build. If they cannot get this commitment, the customers, the investment, and the jobs that are supported by data centres will go elsewhere.”
Big Sydney projects still seeking power include those proposed by Goodman Group at Eastern Creek, NextDC’s planned S7 complex, Stack Infrastructure’s SYD1 and AirTrunk’s S4 complex.
Delays in connecting power could push the completion of these projects into the next decade, raising questions over Sydney’s status as a gateway market at a time when regional competition is rising.
The squeeze is expected to be most acute on more marginal schemes that are not yet connected and where developers have only optioned land. Top customers including cloud computing companies, hyperscalers and AI companies also prefer to deal with well-established groups that have the financial muscle to roll out large projects.
Industrial property owner Goodman Group is moving to lease up a former Coles distribution centre where it is planning a $5bn data centre in Sydney’s Eastern Creek which has become a hub for the projects. The company is still going through approvals, but recently sought advice on getting a fresh tenant at the site from early 2027.
That means it may not follow through on its plan to host a data centre.
Industry experts warn there is a lack of capacity until the Sydney Ring South electricity transmission project, which is being built in two phases between 2030–31 and 2033–34, was online.

Partly in response to the squeeze on power in western Sydney, data centre developers have pushed deeper into regional areas with AirTrunk and CDC both targeting sites in regional NSW.
Data centres remain committed to their western Sydney proposals, however. Although privately-held developers declined to comment, Goodman still intends to spend $5bn on developing two 3-to-4-storey data centre buildings with a 500 megawatt capacity.
“Goodman is aware of the increased demand for electrical load connections at 330kV to Sydney West substation,” the group’s plans said.
The company added its timelines are influenced by a range of factors, including approvals and utility connections. “We are currently awaiting further feedback from the relevant authorities regarding the connection timetable,” a spokeswoman said when asked about the status of Project Atlas at Eastern Creek.
The policy landscape is set for more uncertainty with the Minns government proposing reforms to ensure data centres can be supplied electricity without increasing prices and challenging reliability for households and small businesses.
It wants to ensure data centres impose no net costs to other electricity customers, and also fund additional supply of energy.
On NSW government figures, as of July, data centres were seeking network connections with a total capacity of up to 28GW. Data centres seeking around 13GW of capacity were in advanced discussions to connect, with this sum more than the average daily electricity demand in NSW, it said.
However, industry experts cautioned this pipeline does not distinguish between what will actually be built, versus so-called phantom demand, and the timing of demand. Data Centres Australia’s forecast is for 3.9GW by 2030, not 13GW in NSW alone.
The stakes for developers are significant. NSW hosts more than 60 operating or under-construction data centres and had a pipeline of 20 projects valued at $51.4bn.