Almost $40m of public money spent on North Adelaide Golf Course’s controversial upgrade has escaped detailed scrutiny because of financial manoeuvres by the Premier’s department, according to findings in a new report.
An Auditor-General’s review of the project’s first stage found the race to prepare the course for LIV Golf’s 2028 event – now in doubt – sidelined elements including a detailed business case and cost estimates.
Premier Peter Malinauskas in 2025 announced LIV Golf’s shift to North Adelaide from 2028, with the event now threatened by star John Rahm quitting and LIV’s financial struggles.
Auditor-General Andrew Blaskett found the Department of Premier and Cabinet (DPC) approved the direct engagement of 14 specialist consultants, including Greg Norman Golf Course Design, under standard contracts each valued at $55,000.
His annual report, released on Tuesday, found these contracts did not require acquisition plans or purchase recommendations because, under DPC’s procurement policy, they were not over $55,000.
Some “substantial additional services that significantly increased the value of some contracts” were then added.
When these contracts expired, 11 were extended, all worth more than $55,000, with DPC making timely project delivery the main priority.
“We note that this approach limited the opportunity to obtain the benefits of competitive procurement, including market testing, competitive tension and stronger evidence of value for money,” he said in the report.
A total of $38.6m had been spent on the golf course redevelopment by June 30, the report says, which was within the $45m approved for stage one by state cabinet last December.
Mr Blaskett says the upgrade “has the characteristics of a public sector initiative, as it involves the significant redevelopment of a public asset (and) substantial expenditure of public resources”.
“There is, therefore, a risk that significant public sector investment decisions were made without the required analysis of costs, benefits, risks and value for money, reducing transparency and accountability and increasing the risk of inefficient use of public resources,” he says.
The Auditor-General reviewed three procurements and found DPC did not execute a major golf course design services contract until after work had started.
DPC also “did not retain sufficient evidence of its value-for-money assessments” for initial contracts awarded for less than $55,000.
In a response to the Auditor-General, DPC says “extensive effort has been applied to achieve value-for-money outcomes”, but concedes assessment “at project inception was limited by the conceptual nature of the project information at that point in time”.
“The continued focus and achievement of value for money throughout project development has resulted in the final agreed contract sum being considerably less than the initial offers, whilst also increasing South Australian business participation and direct engagement in project delivery,” the DPC response detailed in the Auditor-General’s report says.
Asked in parliament by Opposition Leader Ashton Hurn whether the state government had deliberately structured 14 consultancy contracts “to avoid additional procurement requirements”, Mr Malinauskas said he had received no advice that DPC “made those decisions deliberately” in the way she suggested.
Mrs Hurn, outside parliament, said Mr Malinauskas “was all across the ins and outs of LIV Golf when it was all rosy” but when his department’s spending was being questioned “he says he’s not across the detail”.