PDG entered South Korea last year but is yet to build a data centre in Australia (Image: Princeton Digital Group)
Planning documents filed with the New South Wales government link Princeton Digital Group to an A$1 billion ($701 million) data centre in Sydney’s southwest, which would be the Singapore-based operator’s first facility in Australia.
Drawings by infrastructure consulting firm AECOM filed alongside a request for state environmental assessment requirements label a proposed 100-megawatt data centre at 192 Narellan Road in Campbelltown “PDG Project Genesis”, and name the client as PDG. The SEARs drawing package is marked as a draft issue dated 25 May 2026.
PDG chairman and chief executive Rangu Salgame told Mingtiandi’s MTD TV this week that the company is evaluating sites in Sydney and Melbourne, after appointing energy industry executive Scott Thomas as general manager. He did not identify the Sydney site.
The plan by PDG comes less than a month after Goodman Group withdrew its application for Project Mars, a A$798 million proposal to redevelop an industrial site on Sydney’s lower north shore into a hyperscale facility capable of supporting 81MW of IT load, following heavy opposition from local residents.
First Step to Approval
The request is the first step in the state’s approval process for large projects. Once the planning department issues its requirements, the developer must prepare an environmental impact statement, which serves as the formal development application and goes on public exhibition for comment before the state decides whether to approve the project.

Rangu Salgame, chairman, chief executive, and co-founder, Princeton Digital Group
An Australian Competition and Consumer Commission filing lodged on 30 March shows that Princeton Digital Group Australia is acquiring vacant land in Campbelltown from MH Property No. 1, for the purpose of building, owning and operating a data centre. The competition regulator approved a waiver for the deal on 21 April. Campbelltown is about 44 kilometres southwest of Sydney’s city centre.
The application on the state planning portal is in the name of Sydney residential developer Morehuman Property Group, which commissioned the scoping report supporting the request from consultancy Patch Planning.
PDG and Morehuman did not respond to a request for comment.
Maryfields Estate Site
The 12.71-hectare (31.4-acre) site forms part of the Maryfields Estate, which was rezoned for a mix of business park, housing and seniors living uses following a master planning process that the scoping report says was initiated by the Franciscan Order of Friars Minor in 2014.
The scoping report describes two buildings delivered in stages. The first would be a two-storey, 26-metre high building, and the second a three-storey, 30-metre building. Campbelltown’s Local Environmental Plan, which sets zoning and building controls for the council area, caps building height on the site at 15 metres. The developer argues the extra height is needed to enclose rooftop chillers, cooling towers and generator flues behind acoustic walls. A separate planning proposal with Campbelltown City Council seeks to amend the plan to raise the height limit to 30 metres.
Endeavour Energy issued a connection offer in December 2025 for power supply across three stages, anchored by a 66-kilovolt switching station on site and paid for by the developer, according to the report. Sydney Water has agreed in principle to an interim potable supply that would shift to fully recycled cooling water by late 2031.
That contrasts with Goodman’s experience. Sydney Water told the department in April that it could not support Project Mars progressing without further study of the local water supply zone, and asked for the assessment to be deferred.
With the report describing capital investment of more than A$1 billion, Project Genesis would cost at least A$10 million per MW. That compares with about A$13.2 million per MW for Microsoft’s recently approved Huntingwood facility and A$9.9 million for Project Mars.
Neighbours on All Sides
An urban design site context map filed this month places the proposed data centre in close proximity to Bethlehem Monastery, residential and seniors living zones, a proposed hotel, Western Sydney University and TAFE. The monastery’s buildings sit more than 60 metres from the second data centre building, according to the scoping report. Western Sydney University’s campus is about 600 metres away.
Goodman’s Lane Cove West site sat closer to its neighbours. Project Mars would have stood about 20 metres from the nearest house and 160 metres from Lane Cove West Public School. The proposal drew 374 public submissions, of which only nine were supportive. Residents pointed to the more than one million litres of diesel fuel that could be stored at the facility as a potential risk, according to local news reports.
Project Genesis would rely on 78 emergency backup generators, bulk diesel storage and lithium-ion batteries. The report does not disclose how much diesel would be stored on site. Microsoft’s 96MW Huntingwood project will use 46 diesel generators, with up to 1.5 million litres of diesel stored on site.
The scoping report says the campus would support 900 to 1,100 ongoing jobs at full build-out. The planning department cited 74 operational roles among its reasons for approving Microsoft’s 96MW Honeman Close Data Centre. The lower end of the Genesis estimate is more than 12 times that figure.
Australian Ambitions
Backed by Warburg Pincus, Mubadala and Stonepea, PDG was founded in 2018 and reports more than 1.8 gigawatts of capacity across eight Asia Pacific markets.
Salgame said in his conversation with Mingtiandi this week that existing customers had encouraged PDG to expand into Australia and South Korea.
Neither the scoping report nor the planning portal names PDG. The report says the project responds to contracted demand from cloud providers, government agencies and enterprise users, but does not identify any customers.
Rules Still Shifting
The NSW government released a Data Centre Policy Framework in August that offers faster approvals to projects meeting tougher environmental and resource-use standards, while moving to make developers pay for additional electricity and water infrastructure. The state has set a 75-day assessment target for qualifying projects.
At the federal level, the National Cabinet on 26 August endorsed developing mandatory national standards for large data centres covering energy, water, land use and skills on, with the Commonwealth committing to legislate in early 2027. Prime Minister Anthony Albanese has said the rules would not apply to projects already approved or under construction.
Project Genesis is unlikely to be approved before those standards arrive. The scoping report shows the request for assessment requirements was first prepared for submission in July, with a revised version dated 8 October submitted in October. Microsoft’s Huntingwood application, lodged in 2023, was approved this month. Goodman’s Project Apollo was approved about 16 months after its exhibition period ended.