The City of Stirling could be forced to fork out more than $400,000 to dredge Jackadder Lake as it considers how it will deal with toxic algae which has forced users off the water for months.
An investigation into the Woodlands lake revealed that improving its water quality could initially cost between $140,000 and $210,000, with a major dredging operation potentially adding hundred of thousands of dollars to the bill.
The findings were presented the city’s community and resources committee on October 27 after more than six months of restrictions for users at the popular lake.
The city describes Jackadder Lake Reserve as a “lovely family park” that is “ideal for playing, scooting and cycling”.
Water quality testing in January detected the potentially harmful blue-green algae, which caused the city to install warning signs advising visitors to avoid contact with the water.
Advice from the WA Department of Health recommended discouraging activities in and around the lake until a week after the bloom is cleared.
“The issue is not just contact with the water, it is also inhalation of water aerosols generated by wind over the lake, so any activity that leads to groups congregating at the edge of the water was not advised,” a Stirling officer’s report said.
Camera IconJackadder Lake public safety warning. Credit: Sophie Gannon
Regular testing has continued to detect high levels of the blue-green algae, with recreational water restrictions remaining in place and impacting the Perth Radio Sailing Club and Task Force 72 Model Boat Club.
Earlier this year the city commissioned an independent investigation into the causes of the algal growth at the lake, as well as Talia Lake and Lake Gwelup.
The findings of the investigation have been given to the committee eight months later, with council likely to consider the recommendation at their November meeting.
Camera IconClose up of community notice. Credit: Sophie Gannon
The investigation also found Jackadder Lake’s recurring blooms were likely being fuelled by a combination of stormwater, water diverted from the Osborne Park branch drain, groundwater, and nutrients stuck in sediments at the bottom of the lake.
“Algal blooms have occurred previously and are again evident under current conditions, indicating that this is an ongoing water-quality issue rather than an isolated event,” the report said.
The investigation also found the lake had limited water circulation, low dissolved oxygen, and nutrients were possibly being released from lake sediments.
A consultant has recommended a 12 to 24-month monitoring and investigation program, which would include water quality testing, groundwater monitoring and a sediment survey during the first year.
Camera IconAlgae infested waters. Credit: Sophie Gannon
The proposed works, which also include a trial for a algaecide treatment, are expected to cost up to $210,000.
The treatment alone would cost between $25,000 and $40,000, but officers said that this would provide only temporary relief.
“This cost cannot be a single management response and needs to be considered as a short term treatment option,” the report said.
Officers said monitoring would also be needed alongside the treatment to determine if it was successful and how long the algae levels could be kept below recreational water safety guidelines.
They said the findings needed long-term intervention but more information was needed before a solution could be determined.
A separate long-term management plan would cost an additional $20,000 to $50,000, with future expenses potentially including repeated treatments and dredging every few decades.
“Improving water quality at Jackadder Lake will require a long-term approach involving treatment, monitoring, and further investigation to identify and address the underlying causes of algal growth,” the report said.
If further investigations find the sediments are a major source of the problem, the council could consider dredging the lake.
A feasibility study would cost between $10,000 and $15,000, while the dredging operation is expected to cost more than $400,000.
City officers have recommended the council consider additional funding through its 2027-28 budget or request an earlier start through its mid-year budget review.
Community input would be sought for any proposals on how to deal with the algae.