The first witness called to give evidence at the royal commission examining Victoria’s construction industry said “things changed” when there was a “heavy presence” of CFMEU officials on the job site.
Crane operator Glenn Tyrrell, who worked on a major train bridge project in Melbourne in 2022 which will be the focus of the first fortnight of hearings, told of how he was elected as a health and safety representative on site, and that the project was flowing “really well”, with no union presence.
Mr Tyrrell was on the Sunbury project by way of a labour hire firm, and served as a health and safety representative on the bridge being built over Gap Road.
Counsel assisting the commission, Chris Young KC, on Monday detailed some evidence of how the government-funded project came under the control of the CFMEU in June 2022.
Giving evidence on Tuesday, Mr Tyrell said “things changed” when there was a “heavy presence” of CFMEU officials on site, which could range from two to four union members.
“I don’t think they were allowed to enter. I think they just entered,” Mr Tyrell said.
“They just stopped works. They just come on site and literally stop the whole job.
“They would stand in front of machinery and plant and just tell the operator that he must stop it,” Mr Tyrrell said.
“Their demands were more safety issues that they had concerns with. That was the demands they’d have on their paperwork.”
One instance he recalled was issues with chains, and the CFMEU representatives wanted to check the paperwork on the chains.
“The way I see it is, they can see things from outside of the fence – they’re looking at things – they come on site and they want to test or check or inspect something,” Mr Tyrrell said.
The hearing heard on Monday that the CFMEU repeatedly delayed the project by coming onto the site, and the head contractor and subcontractors documented intimidation from union members.
The CFMEU representatives would sit on water-filled barriers to stop work from happening, Mr Tyrrell said, or walk into areas which forced workers and machines to stop.
Initially when they began attending, conversations between the union reps and management appeared “friendly” but later on there was more tension.
Before June 3, WorkSafe inspectors had not stopped work on the Gap Rd site, and Mr Tyrrell had not called any health and safety stop work orders.
On June 3, the project went into 24-hour work mode, as the train line was shut for 30 days.
That same day, union officials came onto the site, raised safety issues in a way that stopped the cranes and much of the work from going ahead.
On June 6, works resumed. Mr Tyrrell went into a meeting the next day, and was told he would no longer be working for Zoom Recruiting, but instead would be working for BK Labour.
The crane operator said he was told he “had to” join the CFMEU – the first time he had ever joined a union.
Mr Tyrell paid about $1200 in two instalments to BK Labour that year, he said.
There was no difference in the pay rates Mr Tyrrell received under his new labour hire contract.
No lawyers representing any other interested parties had any questions for Mr Tyrrell.
‘Done something wrong there’
Veteran John Holland supervisor Robert Van Den Tol was the second witness to take the stand.
Mr Van Den Tol began working at John Holland in 2008, and was a supervisor for John Holland on the Gap Rd project.
He said there were about 30 to 40 labourers on site at Gap Rd each day, all employed through labour hire companies.
The Gap Rd worksite was “pretty” safe, he said.
Training about when a union official could enter a worksite would have been redundant, Mr Van Den Tol said.
“I don’t think any training would cover it, because they did what they wanted.”
Evidence presented during Mr Van Den Tol’s appearance showed that from January 27, 2022 to June 27, 2022, there were 56 union visits where representatives held Right of Entry notices – one was from ETU reps, all the rest were CFMEU.
The frequency of union visits increased as the 30-day train line shutdown neared, he said.
The 30-day train line shutdown began June 3.
In response to a question from the commissioner, Mr Van Den Tol agreed that when union officials came on site on June 6 and 7, there were no immediate or imminent risks to workers.
“They would just tell them to stop work.
“Depending who or what they were, most of them would stop.”
The CFMEU officials would swear and use derogatory words at the John Holland supervisor, he said.
On June 6 the police were called.
Mr Van Den Tol told police the union officials were trespassing, and the police did “not much”.
WorkSafe was called that day too.
On June 7, the union and bosses at John Holland “began talking”, and then things “calmed down”, Mr Van Den Tol said, and then after that the labour hire company supplying workers changed, and the CFMEU shop stewards were installed at the site.
There was “no difference” in safety before and after the change, he said.
The lawyer representing the CFMEU, Peter Morrissey, pointed Mr Van Den Tol to a WorkSafe inspection note from June 8, which said different protection needed to be put around 11-metre holes.
“It does look like a valid health and safety complaint arising following the visit of the CFMEU health and safety people. Do you agree?” Mr Morrissey asked.
“I would say they’ve done something wrong there, yes,” Mr Van Den Tol said.
More to come
Originally published as CFMEU blocked machinery on major Melbourne project, first royal commission witness reveals