GIGA Storage, a Netherlands-based large-scale energy storage developer, has started building Green Turtle, a 700 MW / 2.8 GWh BESS at Dilsen-Stokkem in Belgium. It is the company’s first storage facility in the country, and it will be made up of 640 Tesla Megapack 3 batteries. Tesla, picked as EPC partner, handles engineering and construction, supplies the batteries and will maintain them over the long term. Earthworks and roadworks started in mid-August on a former zinc factory site on the Rotem industrial estate. That site lies right next to Elia’s 380kV Van Eyck-Gramme line, where the grid operator is building a new substation. Green Turtle will connect to that substation directly, with commissioning planned for the end of March 2028.