Giant batteries storing energy for when UK electricty demand is high will be located in the area.

A blueprint drawn up by NatPower envisions a facility for storing National Grid energy on farmland east of the High Dike road near Stoke Rochford and Great Ponton, south of Grantham.

The size of the site, which will also contain a new electricity substation, is 44 hectares – the same footprint as the Vatican City, or 62 football pitches.

An overview of the proposed battery energy storage facility and electricity substation. Image: NatPowerAn overview of the proposed battery energy storage facility and electricity substation. Image: NatPowerAn overview of the proposed battery energy storage facility and electricity substation. Image: NatPower

South Kesteven District Council’s planning committee heard when it met on Thursday (August 6) that lithium batteries will be in 3.2m tall green-painted containers, and there will be up to 1,142 of them.

A main concern among members was the risk of fire, and the potential for this causing toxic gas or polluted water to be released into the environment.

Marcus Evans from NatPower said he did not know if any similar battery containers had ever caught fire, but said there would be fire detection and dousing measures in each container, to isolate a fire and prevent more than 1,000 containers going up in flames at once.

Coun Helen Crawford (Con – Bourne West) said it was all very well having a 50m buffer around the development, but given recent wildfires across Europe, perhaps there should be a fire break as well. Mr Evans said there would, in effect, be such a fire break in place.

Find out about planning applications that affect you at the Public Notice Portal

Councillors David Bellamy and Ben Green (Reform – Isaac Newton) both put forward opposition to the application, with Coun Green highlighting the proximity to Stoke Park Wood and Old Park Wood.

“Just imagine if containment failed and a serious fire reached those woods,” he stated. “That would be an environmental disaster. Ancient woodland cannot be recreated – once it is gone, it is gone.

“This is the wrong development in the wrong place.”

However, other members of the committee disagreed with their Reform UK colleagues and granted the outline planning application.

NatPower will need to submit more details and have their full plans approved by South Kesteven District Council before the scheme can begin.