A review by the National Audit Office (NAO) of the UK’s planned electricity transmission network upgrades has found that the work, estimated by Ofgem to require £70bn of investment, will be “very challenging” to deliver.
The proposed upgrades are already at risk of not being delivered when needed, and costs to consumers may increase if grid infrastructure impedes the ability of the National Energy System Operator (Neso) to match supply with demand, thus requiring constraint payments to be made.
The Upgrading the electricity transmission network report from the NAO was published today (11 September).
It recommended that the Department for Energy Security and Net Zero (Desnz), Ofgem and Neso work to “strengthen their oversight of the upgrades, improve transparency over the cost and progress of each project, and review options for what to do with new generation projects that are due to connect to the grid before it is ready”.
The problem facing the UK’s national electricity transmission system (NETS) is that increasing numbers of renewable electricity generators are being built but the electricity they produce must be delivered to places where demand is growing – and those two places are often far apart.
“When the grid cannot carry enough electricity from where it is produced to where it is needed, Neso intervenes to keep supply and demand in balance. This has normally meant paying wind farms to turn off and gas plants to turn on,” the NAO explained.
Those payments – called constraint costs – totalled £1.9bn in 2025/26, but NAO’s review found that they “could increase up to £7.8bn by 2030 without concerted action”.
NAO also said Ofgem estimated £70bn of investment in the grid is required between 2025 and 2031, which will increase the network charges paid by consumers by £60 by 2030, “but save them £30 overall compared to the increased constraint costs if projects are not accelerated”.
The review said: “Delivering all the grid upgrades by 2030 will be very challenging. There remain significant planning, supply chain and system access risks and some of the projects are already forecast for delivery after 2030.
“This means some new generation is likely to connect before necessary grid upgrades are complete. It is important to minimise this gap, as delays will increase project and constraint costs and postpone the benefit of achieving clean power.”
It added that many of the 80 projects identified by Neso as necessary in its 2024 Clean Power advice “face significant risks to the delivery of their current forecast delivery date”.
Neso identified “three projects that needed to be accelerated to meet Clean Power 2030 and eight others where acceleration would also reduce constraint costs,” the NAO said, but it warned that there had “not been a significant acceleration in any of these projects so far”.
The NAO said: “In the absence of an integrated plan or whole-system appraisal, the report finds, the government has not demonstrated that these projects represent the best way of achieving its objectives.”
In addition, it found that the proportion of projects that had received an offer of a connection to the grid had fallen from 64% in 2019-20 to 16% in 2023-24.
“The report notes that Desnz, Neso and Ofgem have started to tackle blockages in the system such as planning, access, skills shortages and supply chains,” the NAO said.
In conclusion, it recommended that the three organisations “strengthen their oversight of the upgrades, improve transparency over the cost and progress of each project, and review options for what to do with new generation projects that are due to connect to the grid before it is ready”.
NAO comptroller and auditor general Gareth Davies said: “While Desnz, Ofgem and Neso have started to improve the way they work together, the planned upgrades of the electricity grid will test systems not designed for activity at this pace or scale.
“Value for money now depends on delivery. Failure to implement these necessary grid upgrades will hamper economic growth as well as increase consumer bills.”
Commenting on the report, Public Accounts Committee chair Geoffrey Clifton-Brown said: “Renewables now generate the majority of the UK’s electricity, but the grid has failed to keep pace and is in dire need of upgrading to support the transition to clean energy.
“Years of underinvestment already cost consumers almost £2bn a year in payments to manage network constraints, which may rise to up to £8bn by 2030.
“Desnz, Ofgem and Neso must deliver critical projects on time and provide transparent reporting so Parliament and the public can hold them to account.”
Reacting to the findings of the review, Desnz minister for energy Michael Shanks said: “This report is another stark reminder of the cost of years of historic underinvestment in the grid.
“As the National Audit Office recognises in its report, our once-in-a-generation reforms are finally building the infrastructure we need: reducing our dependence on the fossil fuels that leave households exposed to price spikes and helping lower people’s bills for good.”
An Ofgem spokesperson said: “We’ve introduced reforms to speed up critical infrastructure projects, unblock connection queues and strengthen incentives on network companies to deliver efficiently and on time.
“Protecting consumers and driving down costs remains our priority. Funding is released in stages, costs are rigorously scrutinised and companies face financial penalties if they fail to deliver.
“We welcome the NAO’s recommendations and will continue working closely with government, NESO and industry to improve transparency, strengthen oversight and ensure this investment delivers value for money.”
A Neso spokesperson said: “We welcome the NAO’s recognition that upgrading the grid is essential to reducing long-term costs for consumers and supporting a reliable electricity system.
They added: “While Neso is doing everything it can to keep balancing costs down while maintaining security of supply, reducing those costs over time also depends on Transmission Owners delivering network infrastructure when it is needed, supported by coordinated action across government, Ofgem and Neso.”
The transmission owners are National Grid Electricity Transmission (NGET), Scottish Power Energy Networks (SPEN) and Scottish & Southern Electricity Networks Transmission (SSENT).
Energy Networks Association chief executive Lawrence Slade said: “NAO’s analysis shows how vital investing to upgrade the grid is for the country to save customers money, strengthen energy security and boost the economy. This investment will upgrade our infrastructure, boost energy independence, create thousands of jobs and cement the UK’s position as a clean energy leader—delivering reliable, affordable power for generations to come.
“Long standing Clean Power 2030 targets have helped provide a stable framework for the upgrade work, though from the outset the challenging timescales were seen as possible only through close partnership between Government, industry and regulators.
“Though connections are accelerating, further reform of the planning system is required to allow network operators to go further and faster in work to support achieving these goals. We are also working with our supply chain partners on an integrated Electricity Networks Sector Growth Plan to ensure this investment unlocks growth right around the UK.”
A SSENT spokesperson said: “The National Audit Office report reinforces the importance of accelerating grid investment to help deliver energy security and lower energy bills, through enabling more affordable, homegrown, clean power to meet our future electricity needs. The report also confirms that the cost to bill payers of investing in the grid more than pays for itself through avoided constraint payments and lower electricity costs.
“Last year, our investment in the north of Scotland helped reduce the cost of grid bottlenecks by £300m. The priority now is to keep delivering these vital grid upgrades at pace – to bring down costs, strengthen energy security, and support economic growth in every postcode area.”
The other transmission owners were approached for comment.