Sources at the Rooppur plant said a series of tests would be conducted following the start of the nuclear reaction. The entire process could take 30 to 40 days.
The reactor’s power output will then be increased gradually. Nuclear fuel fission will generate heat, which will be used to produce steam and drive a turbine to generate electricity.
Once the reactor begins producing energy, electricity can be supplied to the national grid when its output reaches 30 per cent of capacity. At that stage, the plant is expected to supply 300 megawatts of electricity, potentially in December.
Plant officials said trial operations could continue for seven to eight months after the initial start-up. Once electricity is supplied to the grid, Bangladesh will become the world’s 33rd country to generate nuclear power.
Rooppur was recognised as a nuclear installation after nuclear fuel arrived at the project site in October 2023. With the receipt of the fuel, Bangladesh also joined the group of countries possessing nuclear energy capabilities.
According to plant sources, once operational, the nuclear power plant will be able to supply electricity continuously at a steady rate, 24 hours a day.
The reactor will require refuelling every 18 months. A unit may remain shut down for up to two months for the removal of spent fuel, loading of fresh fuel and maintenance.
The sources said that once one unit of Rooppur became operational, it could save USD 1 billion annually in fuel imports. However, the project has already been delayed by three and a half years.