The government’s push to introduce a dedicated grid code for AI data centers (AI DCs) by year-end could burden new investment, a lawmaker warned in South Korea’s National Assembly. Cho Kyoung-tae, a lawmaker of the People Power Party on the National Assembly’s Science, ICT, Broadcasting and Communications Committee, said on Oct. 21 that the AI DC-specific grid code being pursued by the Ministry of Climate, Energy and Environment could effectively function as a new regulation, and that the Ministry of Science and ICT, the ministry in charge, should represent the voices of investors on the ground.

A grid code is a set of connection rules that power plants or large electricity-consuming facilities must follow when linking to the power grid. It sets standards requiring facilities to remain connected and supply voltage stably, rather than being immediately disconnected, even when a grid fault occurs. The rules have mainly applied to power generation facilities, but the climate ministry launched an AI data center research group in August and announced it would draw up a dedicated AI DC grid code by year-end, citing the risk that sharp fluctuations in power use during AI computing could destabilize the grid.

At the heart of the dispute is that the regulatory sequence has been reversed. The AI DC Special Act, which passed the Science, ICT, Broadcasting and Communications Committee in April, included provisions allowing AI data centers to trade electricity directly with liquefied natural gas (LNG) power plants, but the measure was dropped from the version passed by the plenary session in May amid opposition from the climate ministry. At the time, the Ministry of Science and ICT and the climate ministry signed a memorandum of understanding pledging to ensure stable power supply through the national grid. “They told us to block direct LNG trading and take electricity from the national grid, and now they are raising the threshold — that doesn’t add up,” Cho said.

Industry players cite uncertainty over the scope and timing of application as the biggest problem. In Ulsan and Donghae, gigawatt (GW)-scale AI data centers have already broken ground or are about to. If the grid code is applied retroactively to facilities whose designs are complete, additional equipment installations would inevitably reduce available space. According to Cho’s office, even a 1% reduction in server capacity would be equivalent, on a 1 GW basis, to wiping out one mid-sized data center of about 10 megawatts (MW).

There are precedents abroad of large projects collapsing due to grid connection delays. Microsoft (MS) recently pulled out of the project in Lawton, Essex, which the British government had promoted as the country’s largest “sovereign AI data center.” The decisive factor was that the local grid operator notified the company it could supply sufficient power only in the early-to-mid 2030s. Project developer nScale is reportedly considering alternatives such as on-site power generation.

A channel for interagency consultation is already in place. The Ministry of Science and ICT and the climate ministry agreed through their memorandum of understanding to form a joint dedicated organization for GW-scale AI DCs, and in July the science ministry launched an “AIDC Megaproject Interagency Support Task Force” involving the climate ministry and others. At the current National Assembly audit, Cho plans to question the Ministry of Science and ICT about its plans to participate in grid code discussions through the interagency task force and what it will demand of the climate ministry to protect projects already underway.

“We should put in place the standards needed for grid safety, but projects already in progress should in principle be excluded from the grid code,” he said. “The Ministry of Science and ICT, the ministry in charge of AI DCs, should actively use the interagency consultation channel to represent the voices of investors on the ground.”

The debate comes as securing power has emerged as a key variable in AI infrastructure investment. As data center power demand surges, countries are overhauling connection rules, but uncertainty over the timing and scope of the regulations is acting as a factor delaying investment decisions. In South Korea, too, GW-scale operators are expected to face inevitable design changes and schedule adjustments until the detailed standards and scope of the grid code are finalized.