Plans for a massive substation are set to be approved later today (Wednesday, October 21).

South Holland District Council’s planning committee have been recommended to give the green light to National Grid’s bid to build a 400kv substation in Weston Marsh.

Photomontage of Weston Marsh Substation A could look PHOTO: NATIONAL GRIDPhotomontage of Weston Marsh Substation A could look PHOTO: NATIONAL GRIDPhotomontage of Weston Marsh Substation A could look PHOTO: NATIONAL GRID

Weston Marsh Substation A is part of the Grimsby to Walpole project which aims to lay 140km of pylons around the Lincolnshire coastline as part of an upgrade to the country’s energy distribution network.

Locals are opposed to this substation, which is due to be built on a location in Marsh Road, north of Weston and near Surfleet Seas End, on the grounds of the loss of top grade agricultural land and the impact on nearby roads.

A report to this evening’s planning committee meeting states that the substation is needed in order to connect the power generated by the Outer Dowsing offshore windfarm into the grid.

How the completed Weston Marsh Substation A could look PHOTO: NATIONAL GRIDHow the completed Weston Marsh Substation A could look PHOTO: NATIONAL GRIDHow the completed Weston Marsh Substation A could look PHOTO: NATIONAL GRID

Did you know you can check other planning applications and all other public notices in your area by clicking here

Earlier this year the Government had approved the application to construct up to 100 wind turbines off the county’s coastline, along with underground cabling from Anderby Creek to a substation in Surfleet Marsh.

Councillors have been told that the wind farm is a ‘critical national infrastructure’ and that the development consent order establishes ‘significant renewable energy and economic benefits’ – which should be given ‘significant weight’ in deliberations for the Weston Marsh substation.

The report states: “Such benefits should be weighed against the localised environmental and community impacts of the proposed substation both in terms of operation and construction. In addition, the proposed development of a substation will facilitate local employment and supply chain opportunities during the construction phase via the skills and employment plan to be secured via a planning condition.

“The proposed substation will cause a number of adverse impacts particularly upon the loss of best and most versatile agricultural land, landscape and visual receptors, cultural heritage and potential disruption to residents during the construction phase. There are however a number of mitigation measures that have been put in place and secured via planning condition to reduce and minimise these adverse impacts as far as practicable.

“With the proposed mitigation secured via planning conditions, the Critical National Priority for the Infrastructure and the substantial weight to be given to benefits improving energy security, supporting economic development and transition to a net zero future in respect of renewable and low carbon energy developments and electricity network Infrastructure, there are considered to be significant material considerations in this case that would substantially outweigh the harm identified, therefore the planning balance is for the proposal.