Private school King’s College is moving ahead with the plans to relocate to the proposed new 3,281m² facility on the site of the former Ursuline Prep School close to Wimbledon village, which shut two years ago.

King’s College acquired the plot, which is in the Wimbledon West Conservation Area, after the prep school closed in 2024. It had been home to the prep school since 1944. 

According to Jestico + Whiles, the idea of retrofitting the existing building was explored but rejected on the basis it would not offer sufficient capacity.

The practice’s design includes a main hall for performances and assemblies, a rooftop learning terrace and a multi-use games area. Specialist rooms for art, design and engineering, and science will also be included.

The new school, approved by Merton Council, will have capacity for 336 pupils aged seven to 11. Current junior King’s College pupils will move from their current Southside campus on Wimbledon Common to the new site, a five-minute walk away.

The application received 24 letters of objection, including one from the Wimbledon Society. The group voiced concerns over a ‘very significant loss of trees’ and a ‘loss of street character’.

However, the group also praised the ‘very positive references to solar, biodiversity, rainwater run-off control and CO2 emissions’.

The facility is aiming to achieve a BREEAM Excellent rating, according to planning documents.

Howard Pye, associate principal at Jestico + Whiles, said the design challenge was ‘a delicate balance of contextual sensitivity to the conservation area and inspiring educational ambition’.

He added: ‘To respond we have used the site’s topography to help inform a series of stepped volumes – The Downs – that host important, shared spaces such as [the] library and hall. 

‘These moves alongside careful consideration of the educational practice of the school will mean junior school pupils of the future benefit from an exceptional educational environment.’

The scheme’s estimated completion date is summer 2028.

The Jestico + Whiles-designed overhaul of St Paul’s Girls’ School, a private school in west London, was completed last year.

Sketch

Project data

Location: The Downs, London SW20 8HR
Local authority: London Borough of Merton
Project type: School
Client: King’s College School Wimbledon
Architect: Jestico + Whiles
Landscape architect: OOBE
Structural and civil engineer: Price & Myers
MEP engineer: Max Fordham
Planning consultant: Bidwells
Acoustic consultant: Anderson Acoustics
Fire consultant: Trigon
Transport consultant: i-Transport
Arboricultural consultant: Arbtech
Whole-life carbon consultant: Troup Bywaters + Anders
BREEAM consultant: Cudd Bentley Consulting
Quantity surveyor: Synergy Construction and Property Consultants
Principal designer: Jestico + Whiles, supported by iM2
Lighting consultant: Max Fordham
Main contractor: TBC
Funding: Undisclosed
Tender date: Summer 2026
Start on site: November 2026 (estimated)
Completion: Summer 2028 (estimated)
Contract duration: TBC
Gross internal floor area: 3,300m²
Form of contract/procurement: Undisclosed
Annual CO₂ emissions: Estimated at 17% below Part L baseline
Total cost: Undisclosed
Planning application reference: 25/P3728