59% of UK energy leaders surveyed by Jacobs have ranked grid or network readiness as one of the top three barriers to being able to deliver energy infrastructure – a higher proportion than leaders in the US, Germany, Singapore and Australia.

The figure was one of several findings from Jacobs’ The Energy Readiness Equation, which was published today [27 October] and featured analysis of 600 energy leaders from the five countries. The leaders are “responsible for strategy, procurement, capital programmes and major project delivery”, Jacobs said.

69% of leaders in the UK believed “sufficient capital” was available for the energy sector, but 31% thought there were “enough investable projects”, the report said.

“Policy and regulatory uncertainty is another major constraint,” the report added. “Seven out of 10 UK respondents rank it among the top three barriers to investment readiness, while 66% identify permitting or land constraints.”

In addition,57% said the readiness of other infrastructure systems outside of their direct control places “a major or critical constraint on energy infrastructure delivery”, according to the report.

Earlier in October, a report from Schneider Electric called The Water Crunch Report, found that 33% of business leaders “expect water quality or availability to become a serious barrier to operations or growth within the next five years”.

Contributors to the research in the Jacobs’ report included Marinus Link, Pub Singapore, Westnetz, Onyx Power, Statkraft, the National Energy System Operator (Neso), Corporate Energy Buyers Association (Ceba), RDQ and National Grid.

Jacobs global low carbon solutions director Alan Fotheringham said: “The UK is making important progress in planning its future energy system, but a plan only delivers value when it becomes infrastructure on the ground.

“The investment appetite and engineering capability are there. What developers need now is greater certainty around grid connections, permitting and the regulatory framework so they can commit capital and resources with confidence.

Jacobs president of global operations Patrick Hill said: “There is no single organisation, sector or geography with all the answers to the energy security challenge, but there is a lot we can learn from one another.

“From our own experience, delivery improves when the industry shares what works and addresses dependencies earlier – with governments, regulators, investors and delivery teams working from a collective view of what is needed.

Neso strategic energy planning director & chief engineer Julian Leslie said: “It is much harder to invest if businesses can see only five years ahead.

“A credible long-term plan gives industry and those financing the energy transition the confidence they need to decision-make.”

Reacting to the report, an Ofgem spokesperson said: “We know lengthy grid connection waits can hold back viable projects and investment.

“That’s why Ofgem is introducing reforms to speed up critical infrastructure projects, unblock connection queues and strengthen incentives on network companies to deliver efficiently and on time.”

The spokesperson added: “Alongside this, we’re supporting major investment to expand and strengthen the UK electricity network, helping unlock economic growth while ensuring consumers get value for money.”

A Department for Energy Security and Net Zero spokesperson said: “Britain’s outdated grid is holding the country back.

“New wind farms, solar projects and businesses are stuck waiting years for connections, keeping us reliant on global fossil fuels and driving up costs for households.

“That’s why we’re tackling decades of historic underinvestment by reforming the connections queue, launching Great British Grid to unlock billions of pounds of public and private investment, and ending the red tape that slows projects down by allowing developers to build their own connections.”

Also in October, NCE reported that the development of an Nscale data centre in Essex faced uncertainty following Microsoft’s withdrawal as the sole publicly confirmed customer. The withdrawal was linked to concerns over delays to electricity grid power supply.

Meanwhile, on 20 October, companies involved in running and upgrading the UK’s electricity transmission and distribution networks said in their Electricity Networks Sector Growth Plan that they expect £58bn of gross value added (GVA) to the economy by 2035, after investing £200bn over the next 10 years.

Like what you’ve read? To receive New Civil Engineer’s daily and weekly newsletters click here.