Centre for Cities’ latest report, Licence to build, argues that centralisation has made it more difficult and more expensive to build new transport infrastructure. 

Rail is one example. With cheaper operation, greater capacity and faster speeds, Britain’s ambition to electrify its rail network dates back to the 1955 Modernisation Plan. Yet seven decades later, just 39 per cent of Britain’s network has been converted, compared to 58 per cent across the EU.  

However, parts of the UK are making progress. Our recent research points to Scotland, where a devolved model has coincided with more consistent and cost-effective delivery – offering lessons for Britain’s railways and cities. 

Scotland offers a different model for rail investment 

Recent electrification projects illustrate the contrasting experiences of Scotland versus the rest of the UK.  

The Maidenhead–Cardiff scheme saw costs rise £1.7 billion above initial estimates and faced delays of up to three years, following inadequate surveys and unforeseen bridge modifications. 

A year prior in Scotland, the Shotts Line became the fifth electrified route between Edinburgh and Glasgow. Despite the collapse of a major contractor, unexpected ground conditions and extensive bridge works, it met its timetable and at less than half the per-kilometre cost of Maidenhead–Cardiff. 

One difference is that Scotland’s devolved model gives Ministers a dedicated rail investment strategy and budget, alongside responsibility for publicly owned ScotRail.  

As shown in Figure 1, Scotland’s electrification costs have fallen 26 per cent in recent years, and are now 20 per cent below England’s. 

Figure 1: Scotland has delivered complex electrification projects at lower cost
scatter visualization

 

As shown in Figure 2, these cheaper costs have coincided with a larger share of the Scottish network undergoing electrification than in England since 2010.  

Figure 2: New electrification has been proportionately faster in Scotland  
chart visualization

 

Scotland’s pipeline rests on more than funding certainty 

Longer-term funding alone does not explain the difference in delivery. England and Wales share the same five-year funding cycle and infrastructure provider as Scotland.  

Nor can Scotland’s performance be attributed to more funding – it delivered 22 per cent of Britain’s new electrification between 2014 and 2024, with only 10 per cent of rail enhancement expenditure. 

One possible explanation lies in how Scotland has exercised its devolved powers. 

Following the transfer of rail powers in 2005, Scottish Ministers used their new responsibilities to mandate a continuous electrification programme in 2012, strengthening this in 2017 with explicit requirements for dedicated expertise and in-house equipment. 

While devolution does not guarantee better delivery on its own, it can better align investment decisions with their wider economic returns and political accountability. Across a smaller geography, Scottish Ministers can better weigh competing policy priorities and, through ScotRail, the longer-term operating benefits. Reduced democratic distance also brings them closer to affected commuters and businesses, strengthening political incentives for successful delivery. 

These lessons could extend to more localised transport infrastructure, particularly as devolution advances at a city-region level south of the border. 

Scotland should take devolution further 

The Scottish Government can be proud of its electrification record and there is scope to replicate the principles of its success at a more local level within Scotland itself. 

In Glasgow, the absence of a Glasgow city-region authority has fragmented responsibilities and left Clyde Tunnel in a financing deadlock. With no ability to distribute costs among the eight constituent authorities, the City Council faces the entire £820,000 annual maintenance shortfall, 10 per cent of its entire budget

Glasgow’s councils have already begun exploring a city-region devolution deal. As the largest British city without a combined authority, this is overdue. More power, funding and responsibility for urban infrastructure has the potential to unlock more economic growth for the whole region.