Rooppur is the largest single project in Bangladesh’s history. The Bangladesh Atomic Energy Commission, under the Ministry of Science and Technology, is implementing the project. The state-owned Nuclear Power Plant Company Bangladesh Limited (NPCBL), under the commission, is responsible for operating the plant. Russian contractor Atomstroyexport is constructing two 1,200-megawatt units at Rooppur.
NPCBL Managing Director Md Zahedul Hasan told Prothom Alo that BAERA had approved the power start, or C-stage, on Thursday afternoon.
“Some tests will be conducted during this stage as well. Power generation will begin at zero. Once the power output rises from zero to 30 per cent, trial electricity supply to the national grid will begin,” he said.
People involved with the project said physical tests are conducted to assess the behaviour of the nuclear reaction inside the reactor vessel. The tests also verify whether all equipment associated with power generation is functioning properly. This is a crucial stage before electricity generation begins. BAERA approval is required before the plant can proceed to each stage.
Sources at Rooppur said the plant would initially generate thermal energy at a limited level, which would then be gradually increased. With the approval of the C-stage, the plant has crossed another major milestone towards connecting to the national grid for the first time. Every stage will be carried out in compliance with the highest safety standards, approved procedures and regulatory requirements.