The development consent order (DCO) for National Grid Electricity Transmission’s (NGET’s) 2GW Sea Link subsea cable project has been approved by the Department for Energy Security and Net Zero (Desnz).

The project would connect Pegwell Bay in Kent to the Suffolk coast between Aldeburgh and Thorpeness, spanning approximately 138km and is designed to reduce pressure on existing grid connections.

The initiative is part of the larger Great Grid Upgrade initiative, responding to an anticipated doubling of energy demand in the UK.

The Sea Link aims to facilitate the delivery of renewable and low-carbon energy sources, which are increasingly essential in meeting national energy goals.

About 122km of the cables will be laid beneath the sea, with additional underground links to be established to converter stations. These stations will play a crucial role in distributing electricity to East Anglia, Kent and other regions of the country.

“The UK Government community benefits scheme will be delivered by National Grid with over £1M each for community funds in Kent and Suffolk,” the government said today [30 October].

National Grid project director for Sea Link Adrian Pierssene said: “This decision is an important step forward for Sea Link and for the electricity network in England and Wales.

“Sea Link will help the network carry more secure and home-grown power to where it is needed. It will also support the jobs, skills, and supply chain needed to deliver The Great Grid Upgrade.”

He added: “Our focus now is on detailed delivery planning, working closely with local partners and keeping communities informed before and during construction.”

Desnz minister of state Michael Shanks said: “Britain’s future rests on rebuilding the national grid so renewable energy and businesses can connect, driving economic growth and reducing our exposure to volatile global fossil fuel markets, which are driving up all our bills.

“By rewiring Britain, we get homegrown power to where it’s needed, we make sure the grid is resilient for the future and we bring bills down for good.”

In July, Members of Parliament (MPs) said the £2.1M community benefits fund allocated by National Grid from its Sea Link electricity interconnector project was so small in comparison to the total value of the £1.1bn project that it could be seen as a “rounding error”.

Yesterday [29 October], speaking in the House of Commons, MP for Herne Bay and Sandwich – a Kent constituency – Roger Gale said: “The figures underpinning the business case for National Grid’s ludicrously environmentally damaging Sea Link project have been shown to have been fiddled together in cloud cuckoo land.

“The Energy Secretary is due to issue her determination on the planning inspector’s inquiry into that scheme imminently.

“Will the Leader of the House, with his usual courtesy, seek to ensure that that announcement is made on the Floor of the House, and not slipped out in a written answer on a non-sitting Friday?”

Responding, leader of the House Alan Campbell said: “I understand the right hon. Gentleman’s concerns about these matters and the way that announcements are made.

“I will take away his point, and I will do my very best to make sure that the announcement is made in the appropriate way.”

The announcement was made at just past 4pm on Friday 30 October.

Main image: A stock photo of a subsea cable. 