Extreme temperatures over the summer contributed to blackouts in areas across the UK, admitted National Grid.

The company revealed the details of the outages in its latest half-year results, covering the six months to 30 September 2026.

“In UK Electricity Distribution, network stability was maintained, but additional localised outages were experienced because of the significant increase in extreme heat during the UK summer period,” the report stated. 

June, July and August saw some of the hottest and driest periods on record for the UK, with a succession of heatwaves and hardly any rain across large parts of the country. 

Extreme heat can affect grid infrastructure, causing components to overheat, transmission lines to expand and sag, and protective equipment to trip, potentially resulting in power cuts.

In response to these risks, the government issued mobile phone alerts to residents across the Midlands and the South in early August, warning that power cuts were increasingly probable.

The National Energy System Operator (Neso), which is responsible for balancing electricity supply and demand in real time to keep the power on, said that no blackouts occurred in July and August.

However, an investigation was subsequently launched into an incident in June, after a whistleblower alleged that Neso had concealed an increased risk of blackouts during the summer. They claimed that the system frequency had become unstable and fallen below Neso’s normal operating limit. Had it continued to fall, this could have led to deliberate, localised power cuts to prevent the wider system from collapsing.

Although the investigation found no evidence of a cover-up, the incident highlights the growing fragility of the national electricity grid.

Its aging infrastructure is not only coming under strain from climate extremes, but the growth of renewable energy sources is compounding the challenge of connecting new generation to an already constrained network.

Energy regulator Ofgem estimates that £70bn of investment is required in the grid between 2025 and 2031 to expand and reinforce it. 

In 2023, National Grid announced its Great Grid Upgrade, the largest overhaul of the electricity grid in generations. The programme aims to expand and modernise the British grid system to allow for connections to new generation sources and upgrades of current infrastructure.

In September 2026, the government launched the Great British Grid, a publicly-owned entity tasked with injecting public funding and fast-tracking grid connections.

In his Autumn Budget speech last week, Chancellor John Healey reiterated the government’s commitment to it. “We will build cheaper, faster grid connections through GB Grid and reform the complex web of institutions that govern the system,” he said. 

However, any upgrades to the grid must take account of the effects of extreme temperatures, both hot and cold. This is according to the recent State of the Climate for the UK Energy Sector report, recently published by the Royal Meteorological Society, which assessed the influence weather had on electricity generation, prices and supply interruptions.