Open this photo in gallery:

Nemaska Lithium is shown under construction in Bécancour, Que., last year. Rio Tinto Group owns a roughly 54-per-cent stake in the plant, while the balance is held by the province.Christinne Muschi/The Canadian Press

Rio Tinto Group is laying off dozens of workers at its Nemaska Lithium Inc. unit in Quebec as the Anglo-Australian mining giant scrambles to find a profitable path forward for the business in the face of market instability.

The company informed workers at Nemaska that it will cut jobs at its lithium processing plant in Bécancour, Que., Rio Tinto spokeswoman Vanessa Damha said in an e-mailed statement Tuesday. The facility is being built but the pace of construction was pared back this past spring.

“With less work expected next year and construction activity expected to remain limited, Nemaska Lithium cannot maintain its current workforce,” Ms. Damha said. Affected employees will receive support and a smaller team will remain to manage the site safely and protect the work completed, she said.

The company did not specify the number of employees being let go. Slightly more than half of the 120 employees at the plant will lose their jobs, according to information obtained by The Globe and Mail. The Journal de Montréal first reported the layoffs.

Nemaska Lithium launched in 2007 with plans to develop a mine called Whabouchi to source spodumene, a lithium-bearing hard rock, and start a lithium processing operation. The company later hit major cost overruns, filed for creditor protection and restructured under new ownership. The Quebec government has sunk roughly $1.2-billion into Nemaska since 2018.

Rio Tinto took majority control of Nemaska earlier this year as the mining multinational presses ahead with an expansion of its critical-mineral holdings. It owns a roughly 54-per-cent stake while the balance is held by the province.

Executives with Rio Tinto have been bullish on lithium as a material for stationary energy-storage units and electric vehicles, but they’re pulling back on the speed of development amid uncertain market conditions. Last year, the company mothballed a US$2.3-billion lithium project in Serbia known as Jadar.

Lithium carbonate prices have fallen about 85 per cent since reaching a record high in 2022. The price of the battery material has plummeted owing in large part to excess supply and a significantly slower than anticipated demand for EVs.

Analysts at Citigroup cut their two-year price forecast for lithium earlier this month, saying fears of demand deterioration for the metal have triggered a “lithium reset,” according to Bloomberg.

In March, Rio Tinto slowed the pace of construction of the Bécancour plant in a bid to get a handle on cost overruns. The facility is currently more than 70 per cent done, according to the company, which had been aiming to put it in production in 2028.

That timeline now appears up in the air. Rio Tinto is currently analyzing “the most viable development path” for Nemaska Lithium, including long-term spodumene supply and the scope and sequencing of production at Bécancour, Ms. Damha said.

Rio has also not yet moved forward on the construction of facilities for the Whabouchi deposit, saying it may choose instead to put another Quebec spodumene supply project called Galaxy into production instead. A final decision is expected this quarter.

The miner remains confident in the long-term outlook for lithium and sees “significant opportunity” in Quebec and Canada, Ms. Damha said. She said decisions on further investment and project timing for Bécancour will depend on the outcome of the internal analysis as well as project economics, market conditions and customer needs.

Total capital costs for the Nemaska lithium development project were pegged at US$2.2-billion, according to a calculation based on Rio Tinto’s published financials for fiscal 2025. Roughly one year of work and $500-million is still needed to finish the Bécancour plant, Le Journal reported.

Quebec’s new government, led by Premier Paul St-Pierre Plamondon, has vowed to break from the previous government in its approach to economic development and said it won’t invest any more money into the project. That might force Rio Tinto to seek another investor to join the ownership ranks.

Quebec’s former Coalition Avenir Québec government bet big on the battery industry as a way to stoke future growth. So far, however, it arguably has little to show for the effort as the industry undergoes a sharp correction.

Sweden’s Northvolt AB had plans for a $7-billion battery cell megafactory in the Montreal area that was supposed to be the biggest private-sector project in the province’s history. But Northvolt went bankrupt, and Quebec lost $270-million in the venture.