Rio Tinto (ASX:RIO) has secured electricity to restart an idled production line at New Zealand’s Tiwai Point aluminium smelter, potentially restoring approximately 30,000 tonnes of annual output.

The three-and-a-half-year agreement with Contact Energy (ASX:CEN), announced on 17 November, provides 50 megawatts of predominantly renewable electricity for Line 4.

Rio Tinto expects the restart to begin in October 2027 following operational preparations and commissioning, with full production targeted for December. This would restore the Southland smelter’s annual capacity to approximately 360,000 tonnes, adding about 3% to Rio’s smelting capacity across Australia and New Zealand.

Contact’s market announcement says electricity supply will fall to 25 megawatts during the second and third quarters each year to support national energy security during peak periods.

Line 4 has been idle since April 2020, initially because of the pandemic’s impact on industrial markets and subsequently amid uncertainty over the smelter’s future.

Longer-term power talks continue

The bridging contract allows production to resume while the companies negotiate a longer-term power purchase agreement that could support Line 4 for at least two decades.

Rio Tinto New Zealand Aluminium Smelters General Manager Michelle Henderson says the agreement “enables an early restart of Line 4”.

Under a non-binding letter of intent announced in May, the companies had targeted additional production in 2030, with scope for an earlier restart.

That proposal envisaged the smelter becoming a long-term customer underpinning Contact’s planned Southland Wind Farm. The broader smelter secured long-term electricity contracts in 2024.

Write to France Pinzon at Mining.com.au

Main image: Rio Tinto