The Roberts Bank Terminal 2 container expansion at the Port of Vancouver, a $5.9-billion project, has been designated a project of national interest by the federal government. Ottawa says the move could pull the terminal’s opening forward by up to four years and raise the port’s container capacity by about 50 percent. The announcement came with nearly $2 billion in federal marine-protection spending, but conservationists warned that no mitigation can offset the threat the terminal poses to endangered southern resident killer whales.
Transport Minister Steven MacKinnon announced the listing in Delta, B.C., on Oct. 30. He said it gives the project greater regulatory certainty while maintaining environmental safeguards, and that the port is approaching the limit of its container-handling capacity. The three-berth terminal is designed to add 2.4 million containers of annual capacity. Under the accelerated timeline, it could begin commercial operations in 2035 rather than 2039.
RBT2 is the second project listed under the Building Canada Act, after the Pacific Link oil pipeline on Oct. 1, and Ottawa is framing it as a matter of trade sovereignty. “We cannot afford to let bottlenecks hold back Canadian trade. We need the capacity to move more goods, reach more markets and seize new opportunities, and RBT2 is an important part of that solution,” MacKinnon told reporters, CTV News reported.
B.C. premier-designate Lorne Doerkson welcomed the decision in his first appearance with federal officials since the B.C. Conservatives won the Oct. 24 provincial election. The project, he said, is expected to generate “thousands of jobs, of course, during construction, and support thousands more long-term positions across transportation, logistics, retail and manufacturing sectors.”
Tsawwassen First Nation, which had pressed for environmental assurances, said Canada has committed to upholding them. Chief Laura Cassidy described the nation’s position as “consent, but not unconditional support.” She said its next priority is a breach in the Roberts Bank causeway to give juvenile salmon access to more habitat.
The Wilderness Committee argued that the timing of the listing sidesteps a key Species at Risk Act permit for the whales. “Those adverse effects will still be there, those adverse effects are science-based, and nothing can mitigate the endangerment of the southern resident orcas because of this project,” Lucero Gonzalez, the group’s conservation and policy campaigner, told CTV. The group has vowed to keep fighting the project.

A slow start for a fast-track law
As The Hub reported in June, nearly a year after Parliament passed the Act in June 2025, no project had been designated under it. The Act also created the Major Projects Office and was pitched as a remedy for regulatory gridlock. The first listing came roughly 15 months after passage. In September, the government introduced Bill C-39 to amend the regime.
In a June 11 C.D. Howe Institute memo, George Vegh and Kate Koplovich criticized the Act. Vegh is a senior fellow at the Munk School of Global Affairs and Public Policy, and Koplovich is a senior policy analyst at the institute. “Rather than creating a clearer and more predictable approvals framework, these changes expand federal discretion and further politicize the regulatory process,” they wrote. They also flagged an unresolved question: whether a designation replaces review requirements under the Impact Assessment Act and the Canadian Energy Regulator Act, or merely adds to them.
What the label does for ports
In an October essay for The Hub, former investment banker William Dahmer argued that Ottawa should prioritize infrastructure that enables other investment, naming ports and freight corridors alongside pipelines and power. But he warned that naming dozens of national priorities “will not expand the government’s capacity to evaluate them, resolve competing interests, or issue timely decisions.”
The queue is long. TD Economics counts more than $1 trillion in potential spending across more than 300 announced projects. A 2023 Canada West Foundation paper found the initial planning phase of federal impact assessments averaged 332 days, against a legislated target of 180.
Indigenous participation is another variable in the timeline. RBC Thought Leadership estimated in 2025 that more than 70 percent of major capital projects planned or underway intersect with Indigenous territories. Varun Srivatsan, RBC Thought Leadership’s director of policy engagement, made the case in an RBC-supported Hub DeepDive. “The private sector must recognize that reconciliation is no longer a sideline initiative—it is the competitive edge in getting projects built,” he wrote.
The Roberts Bank listing will test whether the national-interest label delivers speed or simply layers political discretion onto an approvals system already short of capacity. What to watch: whether the 2035 date survives the remaining federal permits, including the whale protections conservationists are focused on, and whether reviewers can keep pace as more projects join the list.
A second megaproject at the same address
RBT2 won’t have Roberts Bank to itself. The Pacific Link pipeline, designated Oct. 1, is slated to end at a new crude export terminal there. Ottawa has said it is working with B.C. to expand the site’s marine terminal. In a July analysis, The Hub’s Alberta bureau chief Falice Chin laid out why that terminal may be the hardest part of the pipeline plan.
Alberta’s submission to the Major Projects Office envisions a 260-hectare complex with tank storage for 6.5 million barrels. A five-kilometre causeway would connect it to two offshore berths built for supertankers, known as very large crude carriers. Loading those ships directly would end the costly practice of transferring cargo from partly loaded tankers to larger vessels off the U.S. West Coast. Jackie Forrest of the ARC Energy Research Institute told Chin that the big ships can move oil across the world for “a dollar or two a barrel.”
The margins are thin, though. Existing Roberts Bank berths sit at depths of roughly 19 to 22 metres, while a fully loaded supertanker draws about 20. That is enough, Chin found, but only barely. The site is also exposed to the Strait of Georgia, unlike sheltered Burrard Inlet, and Fraser River sediment would likely require ongoing dredging.
There is a precedent here too. More than a decade ago, Trans Mountain studied Roberts Bank for its expansion and passed. It cited roughly $1.2 billion in added cost, engineering difficulties, sensitive coastal habitat, and the challenge of fitting another industrial project into a congested corridor next to Delta, Tsawwassen, and Richmond.
In July, the port authority told Chin that Alberta’s plan was still conceptual. It remains an open question how a crude terminal and its tanker traffic would fit alongside RBT2’s construction and permitting, in the same killer whale habitat at the centre of the opposition.