The mandate to develop the Kampala Storage Terminal (KST) was formally handed to Uganda National Oil Company (UNOC) in 2018, following the approval of its strategic roadmap by the Ministry of Energy and Mineral Development (MEMD) in 2017.

Under the strategic roadmap, UNOC’s development plan was based on acquiring a strategic partner with the requisite capabilities to help deliver the project. In February 2019, UNOC commenced the process of selecting a joint venture partner.

The selection exercise attracted 19 expressions of interest, of which six were shortlisted. However, the request for proposals process did not yield positive results at the time.

UNOC Board Chairman Matthias Katamba says changes were made to the project’s course during the process leading to the groundbreaking of the KST last Thursday.

“We embarked on another process to secure a strategic partner in March 2023, and while this was progressing, UNOC was in the infant stages of implementing the petroleum products importation, which laid the foundation for what followed and changed the business concept,” he says.

This foundation was bolstered by the enactment of the Petroleum Supply Amendment Act, 2023, which empowered UNOC to become the sole importer of petroleum products destined for the Ugandan market and supply them to Ugandan oil marketing companies (OMCs).

“In the petroleum supply agreement between UNOC and Vitol Bahrain, Vitol was obligated to and committed to support UNOC with infrastructure improvements at the Jinja Storage Terminal and the development of the KST, both as enabling infrastructure for the sustainable implementation of the sole importation mandate,” Mr Katamba added.

He further explained that the policy change and partnership between UNOC and Vitol Bahrain reshaped the business case for the KST and strengthened its viability, given UNOC’s role as the sole importer of petroleum products destined for Uganda.

Vitol Bahrain is a regional branch of Vitol, a Swiss-based Dutch multinational energy and commodity trading company founded in 1966 in Rotterdam, Netherlands.

The signing of the petroleum products supply agreement, Mr Katamba added, necessitated the suspension of the second round of the partnership search.

“The development of the strategy for the KST was discussed with Vitol Bahrain, and an alignment reached to empower UNOC to be the sole operator of the facility once commissioned.”

The government would later help UNOC negotiate a financing facility for its projects, which resulted in the signing of a financing agreement on December 19, 2025. The funding for KST was included to the tune of $350 million (about Shs1.3 trillion).

UNOC and Vitol commenced a feasibility study review for the development of the KST in September 2024. Oilcom Tanzania was contracted to undertake the studies, under the supervision of both UNOC and Vitol.

Upon approval of the feasibility studies, front-end engineering design for the KST was commenced and completed in June 2025.

The joint review by UNOC and Vitol management of the FEED report concluded that an initial capacity of 225 million litres be developed as the first phase, with subsequent capacity enhancement to 320 million litres under the second phase, subject to the progress of the refinery project.

The approval of the FEED paved the way for the procurement process for the project management consultant and, subsequently, the engineering, procurement and construction contractor. Both processes were successfully conducted and completed.

The facility has secured development and building permits from the Mpigi District Local Government, while a petroleum facility construction permit has been secured from the Ministry of Energy and Mineral Development.

Works on the KST were expected to commence last Friday, with detailed engineering for the project planned to progress towards completion by March 2027. Commissioning is expected within 24 months, by September 2028.

Benefits

Upon commissioning, the facility will provide additional storage capacity, initially of 225 million litres and later 320 million litres, to build in-country stocks and ensure security of supply of refined petroleum products.

It will also become a regional hub for the distribution of refined petroleum products, initially received by trucks, then rail and thereafter pipeline, from various supply sources imported through Kenya and Tanzania and subsequently from the planned refinery.

The project is also expected to create employment and demand for goods and services.

The KST is projected to create about 320 direct jobs, including 70 skilled and 250 semi-skilled positions, while UNOC is expected to employ and deploy about 50 staff to manage the facility’s operations.

President Museveni, who officiated at the groundbreaking, expressed regret that Uganda was initially buying petroleum products through middlemen in Kenya, which he said was costing the government a lot of money.

It has emerged that Uganda was initially getting diesel at $118 (about Shs464,800) per metric tonne, but under the UNOC-Vitol partnership, the price is $83 (Shs326,800).

For petrol, Uganda was getting $97.5 (Shs384,000) per metric tonne, which is now $61.5 (Shs242,200), while aviation fuel was initially $114.25 (Shs450,000) per metric tonne and is now $79.25 (Shs312,000).

The Minister of Energy and Mineral Development, Dr Monica Musenero, said her ministry is planning the development of three regional petroleum products storage facilities to augment the country’s inland strategic storage capacity.

These facilities, she explained, will progressively bring petroleum storage capacity and strategic stocks closer to different regions of the country, improve access to petroleum products and strengthen the resilience of the national supply chain.

She, however, noted that the KST Terminal will require a dedicated road connection to the Mpigi Expressway to facilitate the safe movement of fuel trucks when operations begin.

In the interim, the Engineering, Procurement and Construction (EPC) contractor will need the Buyala-Nakireebe road to be motorable and conducive enough to facilitate the safe transportation of goods and equipment.

She added: “The development of the project will also require water for both the construction and operations phase, and National Water and Sewerage Corporation (NWSC) has been engaged on this matter.”

The Permanent Secretary in the Ministry of Energy, Eng Irene Bateebe, said Uganda’s current total petroleum products storage capacity stands at about 159.7 million litres, including Jinja Storage Terminal (30 million litres), Mahathi Infrastructure, Kauku (70 million litres), and OMCs, which are required to maintain a 10-day stock, with a total storage capacity of about 60 million litres.

“We are consuming 240 million litres per month; so, by deploying this (KST) facility, we will ideally have added a 30-day strategic storage facility,” said Eng Bateebe.

Background

The Government of Uganda currently owns one petroleum products storage terminal, the Jinja Storage Terminal, a 30-million-litre facility located in Jinja. The terminal was developed to hold strategic buffer stocks to be used whenever there were supply challenges.

With the growth in petroleum products demand associated with economic development, the government, through the Ministry of Energy and Mineral Development, acquired and gazetted 299.04 acres of land in Namwabula, Mpigi District, in 2008 for the development of the Kampala Storage Terminal.