AI infrastructure will add approximately 260 GW of capacity from 2028 to 2030, triple the approximately 90 GW added from 2025 to 2027.
Article by: Rita
UBS Group initiates coverage of five AI data center hosting stocks transitioning from Bitcoin mining operations, issuing a Buy rating across the board with an average upside potential of 36%. The grid interconnection locations and low-cost power secured early on by these five companies have become scarce assets for AI infrastructure development. In its infrastructure report released on September 22, 2026, UBS noted that the group holds a total of 4.8GW in leased capacity, with another ~12GW in expansion pipelines, while the market has only priced in signed assets.
Time to power is a core bottleneck for data center expansion. Grid interconnection queues in the US have extended beyond five years, and vacancy rates in the traditional data center market sit below 2%. UBS analyst Ryan Gravett pointed out that AI infrastructure will add approximately 260GW in capacity between 2028 and 2030, which is three times the ~90GW expected from 2025 to 2027.
Average 36% Upside Potential
Target prices and upside potential for the five companies are as follows. Hut 8: $143 target price, representing a 45% upside from the September 18 closing price of $99. TeraWulf: $24 target price, representing a 41% upside from $17. Applied Digital: $38 target price, representing a 35% upside from $28. Core Scientific: $24 target price, representing a 33% upside from $18. Cipher Digital: $23 target price, representing a 25% upside from $18.
In terms of valuation, the five companies are currently trading at 12 to 18 times 2028E EBITDA (earnings before interest, taxes, depreciation, and amortization), compared to approximately 19 times for data center REITs. Both Digital Realty and Equinix trade at 19x 2028E EBITDA multiples. UBS attributes this discount to execution risk, tenant concentration, and renewal uncertainty in non-traditional markets.
Tenant Shift Toward High Credit Ratings
The five companies have secured contracts for 4.8GW in leased capacity following their transition from Bitcoin mining over the past two years. Early tenants were primarily new-age cloud providers relying on credit support from hyperscalers like Google. The recent tenant mix has improved significantly.
Applied Digital signed an 810MW lease between April and June 2026 with Meta (rated AA-). Oracle (rated BBB) contracted for 200MW. CoreWeave’s (rated B+) share dropped from 100% to 30%. Cipher Digital entered into a 286MW lease with Amazon, which acts as the direct investor and commits to covering cost overruns.
Core Scientific signed a 530MW lease with AMD, which provides project financing support and holds warrants. Hut 8 secured a 704MW lease with Nvidia, a tenant rated AA. TeraWulf signed a 401MW lease with Anthropic for a 20-year term.
Improved tenant credit ratings have a direct impact on valuation. UBS estimates that for every 100 basis points increase in cost of capital, the EBITDA multiple compresses by approximately half. Higher-rated tenants can lower financing costs and support higher valuation multiples.
The Power Pipeline Represents Core Optionality
The five companies collectively hold approximately 12GW in unleased power pipelines, with around 6GW entering the hyperscaler pre-leasing window within the next two to three years. UBS categorizes these into three tiers based on visibility. Tier 1 includes high-probability opportunities within the 2027 delivery window, such as Cipher Digital’s 340MW, TeraWulf’s 400MW, and Applied Digital’s 250MW. Tier 2 covers pipelines scheduled for delivery between 2028 and 2029, while Tier 3 consists of long-dated optionality extending beyond 2030.
Cipher Digital’s pipeline is concentrated in Texas, with approximately 95% of its capacity located in the state. ERCOT’s Batch Zero review process creates uncertainty regarding power allocation and commissioning timelines. Cipher has 477MW of capacity within the 2027 delivery window, including 70MW at the Reveille site where interconnection agreements have been approved. Management describes the demand environment as “stronger than ever.”
Applied Digital’s pipelines are spread across North Dakota, Louisiana, and Alabama, insulating them from ERCOT policy risks. The company has secured 1.2GW of natural gas generation units through its joint venture Base Electron, which can begin power supply starting in 2029. Management disclosed that electromechanical equipment procurement stands at approximately 700MW annually.
Hut 8’s pipeline includes an expansion option at the River Bend campus, with original leases containing up to a 1GW incremental capacity option. The company is also evaluating on-site generation solutions, potentially in partnership with Entergy. American Bitcoin’s 567MW of power resources can serve as a backup reserve for AI applications.
Delivery Execution Acts as a Near-term Catalyst
The five companies are currently delivering approximately 720MW, representing 15% of their contracted capacity. By mid-2027, they will deliver an additional 1.6GW, bringing total deliveries to 2.3GW, or 50% of contracted capacity. UBS highlights delivery execution as a key near-term catalyst.
Applied Digital has delivered 175MW, meeting 44% of CoreWeave’s commitment. Core Scientific has delivered 437MW, reaching 75% of CoreWeave’s commitment. Cipher Digital’s Black Pearl site was delivered two months ahead of schedule, and the Amazon lease has already begun generating revenue. Satellite imagery of Hut 8’s River Bend campus shows foundation construction underway, with the first 65MW expected for delivery in Q2 2027.
UBS recommends positioning across the five companies focusing on three key themes. Scarcity in time-to-power supports rental yields and development returns, with Hut 8 and TeraWulf boasting the highest pipeline visibility. Tenant structures are improving from new-age cloud providers to high-rated counterparties, with Applied Digital and Cipher Digital seeing the fastest upgrade in tenant quality. Delivery execution serves as a near-term catalyst, where Core Scientific and Applied Digital lead in progress.
DisclaimerThis article compiles and interprets a third-party broker research report (UBS Group, September 22, 2026) prepared by Chaoxiang Research, incorporating publicly available market information. The ratings, target prices, earnings forecasts, and related assessments cited herein represent the views of the broker’s analysts, reflecting solely the stance of their respective institution, not those of Chaoxiang Research, and do not constitute any investment advice.Markets carry risks; decisions must be independent. This article should not serve as the basis for buying or selling any securities.