The jet fighter sits on the tarmac under cloudy skies.

A U.S. Marine Corps F-35B Lightning II aircraft assigned to Marine Fighter Attack Squadron (VMFA) 533, Marine Aircraft Group 12, 1st Marine Aircraft Wing, prepares to taxi during exercise Keen Sword 27 at Kunsan Air Base in South Korea on Oct. 21, 2026. (Isabella Renaud/U.S. Marine Corps)

The Pentagon does not have a reliable way to track the roughly 26 million F-35 Joint Strike Fighter parts it owns at Defense Department installations and contractor facilities across the globe, according to a new Government Accountability Office analysis.

GAO analysts found the Pentagon’s F-35 office cannot accurately track about $31 billion of F-35 parts it owns, cannot account for parts reported missing and has not sufficiently trained staff members to oversee the status of parts in the program, according to a GAO report published Monday.

The F-35 Lightning II stealth fighter jet is the most expensive weapons program in U.S. history, expected to cost taxpayers nearly $2 trillion over its life cycle, according to GAO. The program has long been plagued by delays, cost overruns and problems with parts management.

“DOD has long-standing and ongoing deficiencies related to the accountability and financial reporting of F-35 parts,” GAO analysts wrote, noting that its inability to properly monitor the program has contributed significantly to the Pentagon’s inability to pass a financial audit. GAO also warned the inventory problems could affect F-35 warfighting capabilities.

GAO recommended that DOD build and implement new, specific procedures to monitor losses of F-35 parts, develop new training for property managers and study its property management program to determine precisely how many officials it needs to better monitor the F-35 parts program. Defense Department officials agreed with the recommendations, GAO reported.

The F-35 is the most advanced fighter jet the United States has developed. The U.S. has built three variants of the aircraft, which is flown by the Air Force, Navy and Marine Corps and more than a dozen American allied militaries.

The new report is the third since 2019 the GAO has published after analyzing the financial management of the F-35 program. It found DOD has “made minimal progress” in implementing GAO’s past recommendations to improve the program. For example, GAO reported, the Pentagon had not fully implemented “periodic physical inventories” of F-35 parts housed at some 700 different locations, which the watchdog first recommended in 2022.

A major problem currently plaguing the program is the inability for DOD’s F-35 joint program office to track in real time parts it owns but which are stored at hundreds of contractor locations, GAO analysts found. GAO estimated about 70% of DOD’s F-35 parts inventory was held at government facilities and 30% were held at contractor-owned locations.

Pentagon officials said they are currently working to establish an interface that would provide the F-35 office “a live connection” between its inventory software and that of prime contractors with F-35 parts.

But GAO also found that the Pentagon’s F-35 office has not established reliable procedures for verifying data from its prime contractors, saying many are “inaccurate and incomplete.”

In many cases, prime contractors do not know the location of F-35 parts held by lower-level contractors, “because the prime contractors do not have visibility of parts held beyond the subcontractor level, such as those held at sub-subcontractor facilities,” GAO found.

DOD officials have also contributed to the data reliability issues, according to GAO analysts who found Pentagon officials had not entered some 17,000 F-35 parts in various phases of maintenance and repair into the logistics database.

GAO also found that some parts were not tracked when they were in transit via commercial shippers, and “may not be included in the inventory records.”

The analysts warned that the Pentagon must improve its F-35 parts tracking or risk even more problems with the program in the future.

“Unless it takes steps to address the identified issues, DOD will continue to struggle with accountability of F-35 parts, which will affect warfighter readiness and DOD’s ability to report reliable information in its financial statements,” the report concluded.