Special Report: Energy Transition Minerals has secured a positive procedural outcome in its long-running legal dispute over the Kvanefjeld rare earths project in Greenland.

The High Court of Greenland has issued a decision on which defendants will remain parties to the proceedings, ruling in favour of Energy Transition Minerals’ (ASX:ETM) subsidiary Greenland Minerals (GM).

The court decided that all defendants except the Greenlandic Parliament and the Self-Government of Greenland will remain parties to the proceedings.

GM can now proceed its claims against the Greenlandic executive authorities, including the Government of Greenland.

The decision follows GM’s withdrawal of proceedings against the Government of Denmark.

“We are pleased with this decision,” said ETM managing director Daniel Mamadou.

“However, this isn’t a moment for celebration: Kvanefjeld should be a mine today, creating jobs in Greenland and supplying rare earths that Europe needs. 

“Instead we remain in litigation. 

“That delay carries a real cost to Greenland’s economy and to Europe’s supply chain ambitions.”

Case moves forward

Kvanefjeld is considered one of the world’s largest undeveloped rare earths deposits. 

It includes significant amounts of neodymium and praseodymium, which are used in EVs, wind turbines and clean energy applications.

Management said the court’s decision was an important outcome for GM, with the case now able to proceed on its merits against the Greenlandic executive branch it has sued.

GM has already presented its substantive case through its writ of summons, with the court directing the remaining defendants to file their response on the merits by October 27, 2026.

The court has also granted the parties until November 10, 2026 to respond regarding the anticipated duration of the oral hearing.

It has indicated the matter could be scheduled for hearing as early as autumn 2027 or the first half of 2028.

“After years of dealing with procedural objections from the defendants, we hope the case will now move to the merits phase, with the court indicating that a hearing could take place from autumn 2027,” Mamadou said.

“We have always been confident in the strength of our claims and are now closer than ever to obtaining a substantive determination.

“We will see this through and remain fully committed to pursuing our rights in respect of the Kvanefjeld project.”

Separately, ETM’s litigation against the Danish Government remains pending and is unaffected by the Greenlandic court’s decision.

Those proceedings have been paused while the main case in Greenland progresses.

ETM and GM are now assessing the decision with their legal advisers and plan to update the market as further information becomes available.

This article does not constitute financial product advice. You should consider obtaining independent advice before making any financial decisions.