On 2 October, Deutsche Bahn began extensive modernisation work on the Hanover–Berlin line. By the end of 2027, the railway infrastructure will have been upgraded across several sections, with the work including the modernisation of tracks, points, electrical systems and certain stations.
One of the most complex projects involves a 52-kilometre section of the high-speed line. The infrastructure, built in the 1990s, is undergoing a complete refurbishment after 30 years of intensive use.
Deutsche Bahn teams will remove the old concrete slabs using specialised machinery, after which they will prepare the foundations and install approximately 16,000 new slabs. Each slab is 6.5 metres long and weighs approximately 10 tonnes.
As part of the works programme, over 214 points will be replaced or installed, along with approximately 357 km of track, 100 km of overhead power lines and 13 km of noise barriers. In addition, 25 stations will be modernised, and some will be adapted to provide access for people with reduced mobility.
Long-distance trains will be diverted
During the works, long-distance rail traffic between Hanover and Berlin will be rerouted via Braunschweig and Magdeburg, and the journey time between the two cities will be approximately 80 minutes longer.
Whilst modernisation work is underway on the Hanover–Berlin line, three long-distance trains will run in each direction every two hours, along with other individual services. Braunschweig and Magdeburg will be connected to the long-distance rail network every hour. Magdeburg will temporarily have more stops than usual.
At the same time, Deutsche Bahn is continuing the phased electrification of the Lehrter Stammbahn, a parallel railway line, and the modernisation of the infrastructure between Hanover and Berlin. Work is planned on six signalling installations and the construction of five line connections.
The company also aims to implement, by the end of 2027, the measures required to increase the speed on certain sections to 160 km/h.
For regional transport, replacement buses will be introduced where trains are unable to run. Deutsche Bahn states that the revised timetables for the period 2 October to 12 December 2026 are already available on passenger information systems.
“It is a huge undertaking, but an investment that will be reflected in the quality, reliability and stability of one of Germany’s busiest east–west rail links,” said Wolfgang Weinhold, coordinator of the corridor modernisation programme at DB InfraGO.